ELE19-03815
| Conference | 10/7/2019 | 10/7/2019 | 10/7/2019 3:13:12 PM | P | PASS |
|
|
as late as possible // Stacy Phone #: ###-####...discussed moving of meter/servicechange for new addition...additional conference will be scheduled once framing done to discuss new addition wiring..pamphlet given...homeowner competent to do work
|
ELE19-03809
| Permanent Service | 10/7/2019 | 10/7/2019 | 10/7/2019 2:21:49 PM | P | PASS |
|
|
This is an emergency panel change/meter base change. Please schedule this for later in the day as IPCO just shut off power - I will have Bruce call you as soon as he is ready for inspection this afternoon so we can restore power - Thank you for your understanding ; patience. Have a nice day! Phone #: ###-#### Inspection requested via web by JENNY EMEL... p/s u/g reconnect ok
|
ELE19-03255
| Rough-In Permanent Service | 10/7/2019 | 10/7/2019 | 10/7/2019 2:09:35 PM | P | PASS |
|
|
Mucho Phone #: ###-####... rough ok to cover p/s u/g new ok
|
ELE19-03697
| Electrical Rough-In | 10/7/2019 | 10/7/2019 | 10/7/2019 1:30:48 PM | P | PASS |
|
|
Ready for rough in inspection in the kitchen. Phone #: ###-#### Inspection requested via web by Tyler Stewart...rough-in kitchen ok to cover
|
ELE19-02828
| Electrical Rough-In | 10/7/2019 | 10/7/2019 | 10/7/2019 12:31:07 PM | P | PASS |
|
|
We would like a rough in for wall cover for this building please? Phone #: ###-#### Inspection requested via web by Tom Jenkins...walls only ok to cover...exterior walls of shell and walls of tenant space
|
ELE19-03808
| Final | 10/6/2019 | 10/7/2019 | 10/7/2019 12:10:13 PM | P | PASS |
|
|
LED panels Phone #: ###-#### Inspection requested via web by Tim Dunlop...UL listed fixtures..replacing existing fixture locations..ok to final
|
ELE17-02337
| ELE-Aging Inspection | 10/7/2019 | 10/7/2019 | 10/7/2019 9:35:24 AM | | FAIL |
|
|
contractor making no attempt to make correctiions and schedule final
|
ELE19-01946
| Electrical Rough-In | 10/4/2019 | 10/7/2019 | 10/7/2019 9:22:28 AM | A | PASS |
|
|
Eddy Phone #: ###-####.... wiring on surface...pvc and metal boxes...proper wire size and grounding..ok
|
ELE19-03350
| Final | 10/4/2019 | 10/7/2019 | 10/7/2019 8:58:49 AM | A | PASS |
|
|
Phone #: ###-#### Inspection requested via web by Rick Berry...UL listing
|
ELE19-03055
| Final | 10/4/2019 | 10/7/2019 | 10/7/2019 8:58:10 AM | A | PASS |
|
|
Randy. Phone #: ###-#### Inspection requested via web by Sean DeLacy... ok to final no card on site
|
ELE19-03498
| Final | 10/4/2019 | 10/7/2019 | 10/7/2019 8:34:05 AM | A | FAIL |
|
|
Phone #: ###-#### Inspection requested via web by Seth Stears... 1) solar panel needs labelled...OCPD need clear, evident, and specific purpose or use....408.4
|
ELE19-02977
| Final | 10/1/2019 | 10/7/2019 | 10/4/2019 12:28:18 PM | A | CANC |
|
|
Brian Prussia Phone #: ###-#### >> Inspection requested via web by BRS Permitting Inspection cancelled from web by: BRS Permitting
|
ELE19-03258
| Final | 10/1/2019 | 10/7/2019 | 10/4/2019 11:00:04 AM | A | CANC |
|
|
Brian Prussia Phone #: ###-#### >> Inspection requested via web by BRS Permitting Inspection cancelled from web by: BRS Permitting
|