ELE17-03720
| ELE-Aging Inspection | 2/12/2020 | 2/12/2020 | 2/13/2020 3:05:33 PM | | DONE |
|
|
final scheduled
|
ELE19-04918
| Electrical Rough-In | 2/12/2020 | 2/12/2020 | 2/12/2020 3:16:53 PM | P | PASS |
|
|
South tower 2nd floor and 1st floor units (8 total) All stairwells and 3rd floor stairwell ceilings. Please call if any issues with pushing any of this to Thursday. 2nd floor and stairwells are priority. Phone #: ###-#### Inspection requested via web by Todd Hall.. ok to cover areas listed above
|
ELE17-00783
| Final | 2/12/2020 | 2/12/2020 | 2/12/2020 2:29:05 PM | P | PASS |
|
|
Chris Phone #: ###-####...ok to final
|
ELE20-00434
| Rough-In Permanent Service | 2/12/2020 | 2/12/2020 | 2/12/2020 2:07:31 PM | P | FAIL |
|
|
Please call Patrick with questions this should be a service/rough in inspection. The address is 12009 W. Camas St. Boise. Sorry for the address error. It should be fixed. Phone #: ###-#### Inspection requested via web by A.M.E. Office... pipe to out building feeding power was not verified and is covered...requiring images or holes be dug to verify depth...service behind fence on small barn-homeowner giving permission to go in backyard for inspection
|
ELE20-00434
| Electrical Rough-In | 2/12/2020 | 2/12/2020 | 2/12/2020 2:04:59 PM | P | PASS |
|
|
Please call Patrick with questions this should be a service/rough in inspection. The address is 12009 W. Camas St. Boise. Sorry for the address error. It should be fixed. Phone #: ###-#### Inspection requested via web by A.M.E. Office... rough-in for shop ok...M/C, conduit, and metal boxes on surface ok...GFCI protection installed with GFCI recps and breakers...for future perm service need pipe depth to building verified by prope holes or pictures
|
ELE20-00464
| Electrical Rough-In | 2/12/2020 | 2/12/2020 | 2/12/2020 12:05:56 PM | P | PASS |
|
|
call on way so i can meet you there. Phone #: ###-#### Inspection requested via web by Kurtis Moore...new garage, storage rm, and entertainment rm ok to cover
|
ELE19-04057
| Electrical Rough-In | 2/11/2020 | 2/12/2020 | 2/12/2020 11:25:45 AM | A | PASS |
|
|
Dirk Phone #: ###-####... rough in ok to cover went over what needed to do to regain grounding for service
|
ELE19-01489
| Electrical Rough-In | 2/12/2020 | 2/12/2020 | 2/12/2020 10:02:03 AM | A | NR |
|
|
Kitchen ceiling cover. Toby is the contact Phone #: ###-#### Inspection requested via web by Buster Bowen...not ready...call when complete...open connections, stubs, boxes...other subs need completetion first
|
ELE20-00481
| Electrical Rough-In | 2/11/2020 | 2/12/2020 | 2/12/2020 9:38:31 AM | A | PASS |
|
|
wall inspection. Contact Kris for questions Phone #: ###-#### Inspection requested via web by Bayley Beard....new wall dividing CPU room creating 2nd rm...wall and drop ceiling ok to cover...door to right past customer service counter
|
ELE20-00396
| Electrical Rough-In | 2/12/2020 | 2/12/2020 | 2/12/2020 9:07:59 AM | A | PASS |
|
|
Phone #: ###-#### Inspection requested via web by Matt Oranday...UL listed equipment verified
|
ELE20-00490
| Final | 2/11/2020 | 2/12/2020 | 2/12/2020 8:36:56 AM | A | PASS |
|
|
Please contact Shannon with any questions. Phone #: ###-#### Inspection requested via web by Deb Morton...15A circuit...disconnect and labelling complete...ok to final
|