Inspections for the day of: Wednesday, June 19, 2019.
Number of inspections: 14
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorTom Saunders
TitleELE-INSPECTOR
Phone #208-794-1923
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
ELE19-00879 Final6/19/20196/19/20196/19/2019 2:28:22 PMPPASS
Please call when you are on your way to the site. Phone #: ###-#### Inspection requested via web by Spencer McLean...
disconnect with GFCI breakers...ok to final
ELE19-00879 Permanent Service6/18/20196/19/20196/19/2019 2:27:48 PMPPASS
Please call when you are on your way to the site. Phone #: ###-#### Inspection requested via web by Spencer McLean...
ok to connect
ELE16-03043 ELE-Aging Inspection6/19/20196/19/20196/19/2019 2:03:09 PM FAIL
contractor making no attempt to schedule required inspection
ELE19-02241 Electrical Rough-In6/19/20196/19/20196/19/2019 1:32:31 PMPPASS
Call son for access // Paul Jesse ###-#### electrican Phone #: ###-####...
wiring ok to cover
ELE19-02220 Electrical Rough-In6/18/20196/19/20196/19/2019 1:02:16 PMPPASS
Bonding and underground cover.
Owner will be home, use east gate to backyard. Phone #: ###-#### Inspection requested via web by Kevin Koomler....
underground ok to cover-light, cover, outlet, and switching
bonding-4 corners, light, and cover
ELE19-01858 Electrical Rough-In6/18/20196/19/20196/19/2019 12:45:39 PMPNR
Phone #: ###-#### Inspection requested via web by Kerri Hamilton...
ceiling grid not yet complete ...LV not done...will need recalled in when complete...electrical contractor not doing work but grid inspection their responsibility
ELE19-01965 Final6/18/20196/19/20196/19/2019 11:18:17 AMAFAIL
Pls contact Brad (Foreman) @ ###-#### or Preston (Electrician) @ ###-#### one hr prior or if you have any questions. Thank you. Inspection requested via web by Rob Maes...

Boise City requires a rough inspection before a final inspection can be requested
this is not contractors first job in Boise City and is fully aware of requirement
materials on roof will be removed and placed on ground for rough inspection...tiles, inverters, etc.
a reinspection fee will be applied to permit and needs paid before future inspections scheduled
ELE19-01498 Final6/18/20196/19/20196/19/2019 10:11:23 AMANR
please call Nick Phone #: ###-#### Inspection requested via web by Kevin Perez...
not ready at this time...needed grid inspection only
ELE19-01498 Electrical Rough-In6/19/20196/19/20196/19/2019 10:10:31 AMAPASS
please call Nick Phone #: ###-#### Inspection requested via web by Kevin Perez...
grid inspection...ok to cover
ELE19-02256 Final6/18/20196/19/20196/19/2019 9:46:17 AMPPASS
Phone #: ###-#### Inspection requested via web by Rob Maes...
up sized fuses and new labelling...ok to final
ELE19-02256 Electrical Rough-In6/18/20196/19/20196/19/2019 9:44:35 AMAPASS
This is a 3 panel addition to an existing system so will most likely be done by 10:30/11am. Give a call prior if needed and I can make sure someone is there to meet you. Thank you! Phone #: ###-#### Inspection requested via web by Rob Maes...
3 panels verified
ELE19-01997 Electrical Rough-In6/18/20196/19/20196/19/2019 9:17:11 AMAPASS
Please call the number above before heading to the jobsite. Phone #: ###-#### Inspection requested via web by BRS Permitting...
UL listed equipment
20A breaker in panel...no access needed for final
ELE19-02206 Electrical Rough-In6/18/20196/19/20196/19/2019 8:53:44 AMAPASS
Available anytime after 7:30.

If no answer at door (Doorbell hard to hear from construction location) call ###-####. Phone #: ###-#### Inspection requested via web by Kirt Palmer....
ok to cover wall for new switch location and floor heat controller
ELE19-02167 Electrical Rough-In6/18/20196/19/20196/19/2019 7:45:46 AMAPASS
Please call prior to arrival Phone #: ###-#### Inspection requested via web by Patrick Paz...inspection done previous day...see notes