ELE18-02951
| Conference | 8/14/2018 | 8/15/2018 | 8/15/2018 3:17:37 PM | P | PASS |
|
|
Call half hour before to meet // Albert Phone #: ###-####... home owner licensed electrician..discussed requirements for new bedroom addition..also service upgrade-requiring move meter to meet 3ft clearance from gas meter..discussed multiple options for new circuits and service upgrade
|
ELE18-02423
| Electrical Rough-In | 8/15/2018 | 8/15/2018 | 8/15/2018 2:13:02 PM | P | PART |
|
|
ceiling rough-in above grid. Dustin is the site foreman Phone #: ###-#### Inspection requested via web by Kerri Hamilton...entry "cloud" cover only
|
ELE18-02563
| Electrical Rough-In | 8/15/2018 | 8/15/2018 | 8/15/2018 1:16:39 PM | P | PASS |
|
|
fireplace install...ok to cover...rough complete
|
ELE18-03118
| Temporary Service | 8/15/2018 | 8/15/2018 | 8/15/2018 1:05:18 PM | P | PASS |
|
|
Phone #: ###-#### Inspection requested via web by ron spen cer...
t/s u/g n ok
|
ELE18-03030
| Rough-In Permanent Service | 8/15/2018 | 8/15/2018 | 8/15/2018 12:37:32 PM | P | PASS |
|
|
Phone #: ###-#### Inspection requested via web by Barbara Szurgot.... corrections made...verify junction box in ceiling for sub feeds at final as well as panel inside is made into a sub panel...heated tile floor will need seperate rough in inspection... p/s u/g ok to connect...being relocated
|
ELE18-00346
| Final | 8/15/2018 | 8/15/2018 | 8/15/2018 11:37:00 AM | P | PASS |
|
|
Call prior to going Phone #: 2083425188 >> Inspection requested via mobile web by Chris Hopkins ...job complete...ok to final
|
ELE18-00346
| Electrical Rough-In | 8/14/2018 | 8/15/2018 | 8/15/2018 11:36:38 AM | A | PASS |
|
|
Call prior to going Phone #: 2083425188 >> Inspection requested via mobile web by Chris Hopkins ..UL listings and disconnects verified
|
ELE18-02022
| Final | 8/14/2018 | 8/15/2018 | 8/15/2018 11:35:30 AM | A | PASS |
|
|
call 15 mins heads up- Richard Phone #: ###-####...met with contractor and discussed scope of work and what needed to be inspected...proper straping of conduit, LV wires off grid, and all junction boxes accessible...job complete ok to final
|
ELE18-02043
| Conference | 8/14/2018 | 8/15/2018 | 8/15/2018 10:20:16 AM | A | PASS |
|
|
Spoke with Tom and confirmed process to set up conference inspection before beginning work to upgrade from 100 amp panel to 200 amp panel. Phone #: ###-#### Inspection requested via web by Jason Anderson...went over requirements for service change...uffer ground be updated with multi branch circuits need updated 1-2 pole 20 and 1-2 pole 15...pamphlet given...owener competent
|
ELE18-03105
| Final | 8/15/2018 | 8/15/2018 | 8/15/2018 9:21:24 AM | A | PASS |
|
|
Wire new attic fan. Please FINAL Phone #: ###-#### Inspection requested via web by Stuart Welton...complete..ok to final
|
ELE18-03105
| Electrical Rough-In | 8/14/2018 | 8/15/2018 | 8/15/2018 9:20:52 AM | A | PASS |
|
|
Wire new attic fan. Please FINAL Phone #: ###-#### Inspection requested via web by Stuart Welton...used existing circuit of old ventalation fan with switch...12/2 romex in attic...ok
|
ELE18-02477
| Final | 8/14/2018 | 8/15/2018 | 8/15/2018 9:18:52 AM | A | PASS |
|
|
Yolanda Phone #: ###-####...ok to final
|