Inspections for the day of: Monday, August 19, 2019.
Number of inspections: 16
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorTom Saunders
TitleELE-INSPECTOR
Phone #208-794-1923
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
ELE19-02372 Final8/19/20198/19/20198/19/2019 3:31:54 PMPNR
Contact: Rob Lawrence Phone #: ###-#### Inspection requested via web by Deb Gooden...
rescheduled next day for PM
ELE19-03084 Final8/18/20198/19/20198/19/2019 2:59:33 PMPCANC
Calling inspector in morning for Questions on tempn service Phone #: ###-#### Inspection requested via web by shane miller...needed temp service for construction of new garage and keep power to existing house that is occupied
ELE19-03084 Temporary Service8/19/20198/19/20198/19/2019 2:55:36 PMPPASS
Calling inspector in morning for Questions on tempn service Phone #: ###-#### Inspection requested via web by shane miller...service moved on house to install trusses to new shop/garage
t/s o/h relocated for construction ok
ELE19-02574 Final8/16/20198/19/20198/19/2019 2:13:28 PMPPASS
Please call Dan Flaherty (owner) 1/2 hour in advance of inspection and he will meet you and let you in. His phone number is ###-####. Phone #: ###-#### Inspection requested via web by sam petterson...ok to final
ELE19-01316 Final8/19/20198/19/20198/19/2019 1:49:22 PMPNR
Exterior Phone #: ###-#### Inspection requested via web by Kevin Burke....
not ready...rescheduled for next day morning
ELE19-03051 Permanent Service8/18/20198/19/20198/19/2019 1:21:46 PMPPASS
Please call ahead of inspection so that I can meet on site. Phone #: ###-#### Inspection requested via web by BARRY KENDALL...
p/s o/h new ok
ELE19-01992 Electrical Rough-In8/16/20198/19/20198/19/2019 11:42:43 AMAPASS
wall cover Phone #: ###-#### Inspection requested via web by David Feller...
wall cover only ok for 3 new offices..103,104,105
ELE19-02767 Electrical Rough-In8/16/20198/19/20198/19/2019 11:28:32 AMAPASS
Phone #: ###-#### Inspection requested via web by Kerri Hamilton...
UL listing on new lay in LED fixtures verified
changing out existing lighting locations-no grid inspection required using existing grid wires
ELE19-03073 Electrical Rough-In8/16/20198/19/20198/19/2019 10:54:10 AMAPASS
Please contact Barry Spencer with any questions or timeline. ###-#### Phone #: ###-#### Inspection requested via web by Rob Maes...
UL listing verified
minus panels...verified by site plans
will need access for final...breaker in panel
ELE19-02749 Electrical Rough-In8/19/20198/19/20198/19/2019 10:11:56 AMAPASS
rough in porte cache...rough in ok to cover...surface mounted lights underneath, 2 lights on top, and perimiter interior lighting
ELE19-02542 Electrical Rough-In8/19/20198/19/20198/19/2019 9:59:24 AMACANC
Porte Cochere Rough-in Phone #: ###-#### Inspection requested via web by Dan Cox...
wrong permit
ELE19-02348 Electrical Rough-In8/16/20198/19/20198/19/2019 9:42:46 AMAPASS
We need an underground inspection please. Thank you Phone #: ###-#### Inspection requested via web by Tom Jenkins...feeds to building from transformer and feeds from main building to other building
ELE19-03082 Final8/17/20198/19/20198/19/2019 9:17:29 AMAFAIL
Homeowner said he would be there. Trench is still open, and wiring inside is not going to get covered. GFCI Bkr in meterbox, #12 THHN in conduit to shed, and 12-2 MC inside with metal boxes that have gnd pigtails. Give me a call if there''s any questions. Phone #: ###-#### Inspection requested via web by Dan Hilke...
1..accessory building shall have luminaire on exterior...210.70(2)(2)
2..disconnect needs installed...225.31
ELE19-03082 Electrical Rough-In8/19/20198/19/20198/19/2019 9:05:44 AMAPASS
Homeowner said he would be there. Trench is still open, and wiring inside is not going to get covered. GFCI Bkr in meterbox, #12 THHN in conduit to shed, and 12-2 MC inside with metal boxes that have gnd pigtails. Give me a call if there''s any questions. Phone #: ###-#### Inspection requested via web by Dan Hilke....
trench ok to cover
interior rough in ok
ELE18-02523 Electrical Rough-In8/17/20198/19/20198/19/2019 8:43:47 AMAPASS
2nd floor west side Phone #: ###-#### Inspection requested via web by Debby Pierce...
TCO 2nd floor and vestibule...marked on mini plan print
ELE19-03074 Conference8/16/20198/19/20198/19/2019 8:18:51 AMAPASS
Hello Tom, I would like to schedule our conference first thing in the morning Monday. Thanks and see you then.
discussed requirements for kitchen, laundry, and bathroom remodels...pamphlet given...homeowner has done work previously
Steve Phone #: ###-#### Inspection requested via web by Steven M Bandkau Jr