PLM17-04069
| PLM-Aging Inspection | 10/18/2018 | 10/18/2018 | 10/19/2018 8:12:31 AM | | NR |
|
|
Work not completed per contractor; waiting on owner.
|
PLM18-04389
| Final | 10/18/2018 | 10/18/2018 | 10/18/2018 4:11:45 PM | P | FAIL |
|
|
LATE P.M. FINAL PLEASE Phone #: ###-#### Inspection requested via web by Aaron Alandt The cpvc female adapter must be metal x cpvc.on the fip end. Drill a 1/8" hole in the lowpoint of the t&p drain where trapped.
|
PLM18-04371
| Plumbing Rough-in | 10/18/2018 | 10/18/2018 | 10/18/2018 3:52:25 PM | P | PASS |
|
|
Phone #: ###-#### Inspection requested via web by Brian Johansen
|
PLM18-02570
| Plumbing Rough-in | 10/17/2018 | 10/18/2018 | 10/18/2018 3:37:04 PM | P | PART |
|
|
BRAD IS THE JOB CONTACT ###-#### Phone #: ###-#### Inspection requested via web by BECCA DUMMER rr ok to cover. Vent through the fire wall shall be changed to cast iron
|
PLM17-03783
| Final | 10/17/2018 | 10/18/2018 | 10/18/2018 3:10:26 PM | P | PASS |
|
|
Phone #: ###-#### Inspection requested via web by Brian Johansen
|
PLM17-04251
| Final | 10/17/2018 | 10/18/2018 | 10/18/2018 3:09:10 PM | P | PASS |
|
|
|
PLM18-04001
| Water and/or Sewer | 10/17/2018 | 10/18/2018 | 10/18/2018 3:08:44 PM | P | CANC |
|
|
Hi Dan...thanks for stopping by on Tues and Wed. I fixed the mistake on the kitchen sink drain pipe. I also took pictures of the work completed in the crawl space. There’s a pony wall the length of the house (side to side) that’s pretty tight to pass through. I can show u those pictures if you are able to stop by in the afternoon on Thursday. Phone #: ###-#### Inspection requested via web by Michael Koltonski
|
PLM18-04001
| Plumbing Rough-in | 10/18/2018 | 10/18/2018 | 10/18/2018 3:08:35 PM | P | PASS |
|
|
Hi Dan...thanks for stopping by on Tues and Wed. I fixed the mistake on the kitchen sink drain pipe. I also took pictures of the work completed in the crawl space. There’s a pony wall the length of the house (side to side) that’s pretty tight to pass through. I can show u those pictures if you are able to stop by in the afternoon on Thursday. Phone #: ###-#### Inspection requested via web by Michael Koltonski
|
PLM18-03819
| Final | 10/17/2018 | 10/18/2018 | 10/18/2018 2:07:29 PM | P | NR |
|
|
Call for access if needed Phone #: ###-#### Inspection requested via web by Bill Harmon
|
PLM18-02963
| Water Heater Final | 10/17/2018 | 10/18/2018 | 10/18/2018 11:07:11 AM | A | FAIL |
|
|
Please call the Home Owner Kurt at the number provided when en route and with any questions. Thank you Phone #: ###-#### Inspection requested via web by Ben Davis Install a drip leg on the gas line. reschedule and send me a picture
|
PLM18-04305
| Other | 10/11/2018 | 10/18/2018 | 10/18/2018 10:52:04 AM | A | CANC |
|
|
Test flu pipe for tankless water heater install. Final inspection will be scheduled at another time. Phone #: ###-#### Inspection requested via web by McKenna Haycock 5psi
|
PLM18-04219
| Groundwork | 10/17/2018 | 10/18/2018 | 10/18/2018 10:33:08 AM | A | FAIL |
|
|
call nick for access code for key lock to get into the house. Phone #: ###-#### Inspection requested via web by Nick Marsala 1. The 3" drain is flat. Provide a 1/4"/ft grade. 2. Install a 3" cleanout above the floor or within 5 feet of the crawl. 3. The cast iron to plastic transition must be done with an approved shielded band
|
MIS18-00406
| PLM-Conference | 10/17/2018 | 10/18/2018 | 10/18/2018 9:49:12 AM | A | NH |
|
|
working without permits Phone #: ###-#### I left a correction notice for mechanical and plumbing to pull permits for any plumbing or mechanical work done including appliance changeouts
|
PLM18-04384
| Groundwork | 10/17/2018 | 10/18/2018 | 10/18/2018 9:22:21 AM | A | PASS |
|
|
Please call Don, Thank YOU! Phone #: ###-#### Inspection requested via web by Rhonda Marcum floor drains
|
PLM18-02764
| Plumbing Rough-in | 10/17/2018 | 10/18/2018 | 10/18/2018 9:07:59 AM | P | CANC |
|
|
BRAD IS THE JOB CONTACT ###-#### Phone #: ###-#### Inspection requested via web by BECCA DUMMER
|
PLM17-03152
| PLM-Aging Inspection | 10/18/2018 | 10/18/2018 | 10/18/2018 8:43:55 AM | | NR |
|
|
|
PLM18-04347
| Final | 10/15/2018 | 10/18/2018 | 10/18/2018 8:42:24 AM | A | PASS |
|
|
hoping for a first morning appointment. Please call Matt ###-#### Phone #: ###-#### Inspection requested via web by Nick Drake
|
PLM18-04126
| Water Heater Final | 10/17/2018 | 10/18/2018 | 10/17/2018 4:20:43 PM | A | PASS |
|
|
Re-inspection Phone #: ###-#### Inspection requested via web by Heidi Lukecart
|
PLM17-04485
| Final | 10/17/2018 | 10/18/2018 | 10/17/2018 2:04:40 PM | P | CANC |
|
|
Phone #: ###-#### >> Inspection requested via web by Brian Johansen Inspection cancelled from web by: Brian Johansen
|