Inspections for the day of: Tuesday, February 14, 2012.
Number of inspections: 11
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorBob Reichert
TitleELE-INSPECTOR
Phone #794-1923
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
ELE12-00297 Temporary Service2/14/20122/14/20122/14/2012 2:41:36 PMPPASS
Phone #: ###-#### >> Inspection requested via web by Emmet Bushman t/s u/g n ok
ELE05-02592 Final2/13/20122/14/20122/14/2012 2:27:06 PMPPASS
Sherri Phone #: ###-#### corrections made, ok final
ELE12-00301 Temporary Service2/14/20122/14/20122/14/2012 2:25:36 PMPFAIL
Phone #: ###-#### >> Inspection requested via web by Neal Rumsey called, left correction notice, NEC 110.26(A) shall provide workspace about equipment, 110.14 shall provide tight, good connections at transformer
ELE12-00273 Electrical Rough-In2/14/20122/14/20122/14/2012 1:44:14 PMPFAIL
mike called, left message, left correction notice, NEC 342.26 there shall not be over 360 degree bend in raceway
ELE11-02785 Final2/13/20122/14/20122/14/2012 12:22:34 PMPPASS
Call if any problems Phone #: ###-#### >> Inspection requested via web by Zane Robertson ok final, signed card
ELE10-02086 ELE-Request for Extension2/13/20122/14/20122/14/2012 9:51:39 AMAPASS
Jeremy (or house is ###-####) Phone #: ###-#### extension ok
ELE11-02855 Electrical Rough-In2/13/20122/14/20122/14/2012 9:21:04 AMAPART
Please inspect portion of slab...Get with Bud.

Thank you Bob! Phone #: ###-#### >> Inspection requested via web by Kevin Perez ok cover u/g south part office area
ELE12-00289 Final2/13/20122/14/20122/14/2012 8:45:39 AMACANC
Please inspect the temp service, call Bud at ###-####. Phone #: ###-#### >> Inspection requested via web by Kevin Perez see t/s
ELE12-00289 Temporary Service2/14/20122/14/20122/14/2012 8:45:25 AMAPASS
Please inspect the temp service, call Bud at ###-####. Phone #: ###-#### >> Inspection requested via web by Kevin Perez t/s u/g n ok
ELE09-01607 ELE-Aging Inspection2/14/20122/14/20122/14/2012 7:18:07 AM DONE
still under construction
ELE11-00557 Final2/13/20122/14/20122/13/2012 1:20:11 PMACANC
Please note - this is a final for the Phase One area only. Contact onsite is Glen Corbeil ###-####. Phone #: ###-#### >> Inspection requested via web by Scott Campbell Inspection cancelled from web by: Scott Campbell