Inspections for the day of: Monday, October 28, 2019.
Number of inspections: 13
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorEric Story
TitleELE-INSPECTOR
Phone #985-3493
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
ELE19-03966 Electrical Rough-In10/28/201910/28/201910/28/2019 2:32:32 PMPPASS
listing inspection for solar equipment; the guys will be there around 12 pm but not sooner.

PLEASE NOTE - THIS PROJECT IS AN ADDITION; so there will already be old panels on the roof. We have not started the additional panels until we get the listing inspection. Our last rough in was failed because the guys had left the site and the inspector saw that panels were already up. Give me a call if you have any questions, thanks guys Phone #: ###-#### Inspection requested via web by Ryan King Listing of panels for addition of Solar Array panels to existing system ok
ELE19-03053 Final10/28/201910/28/201910/28/2019 2:27:27 PMPPASS
Justin Metcalf ###-#### Phone #: ###-#### Inspection requested via web by Samatha Solberg
Final ok-Occ card signed
ELE19-04095 Electrical Rough-In10/28/201910/28/201910/28/2019 1:44:05 PMPCANC
Phone #: ###-#### Inspection requested via web by BRS Permitting
Scheduled for wrong day and will re-schedule for 10/29
ELE19-03683 Electrical Rough-In10/28/201910/28/201910/28/2019 1:06:21 PMPPASS
David Phone #: ###-####
Rough-in ok to cover
ELE19-04149 Temporary Service10/28/201910/28/201910/28/2019 12:57:39 PMPPASS
Phone #: ###-#### Inspection requested via web by Chris Berthelot
t/s o/h n ok
ELE19-01023 Final10/28/201910/28/201910/28/2019 12:33:20 PMPCANC
Inspection requested via web by John Edwards
Not ready
ELE19-04008 Final10/28/201910/28/201910/28/2019 12:03:20 PMPPASS
Please call Zack when you''re on your way ###-#### Final inspection for (7)outlets in ceiling and added 100amp main breaker panel interior. Phone #: ###-#### Inspection requested via web by Kendra Lanham
Final ok
ELE19-03455 Final10/26/201910/28/201910/28/2019 11:19:25 AMAPASS
Service change is done. Phone #: ###-#### Inspection requested via web by Craig Korell
Service change final ok
ELE19-03995 Electrical Rough-In10/25/201910/28/201910/28/2019 11:00:06 AMAPASS
Kenny Phone #: ###-####
Kitchen and bath ok to cover
ELE19-03947 Electrical Rough-In10/25/201910/28/201910/28/2019 10:59:42 AMAPASS
Phone #: ###-#### Inspection requested via web by Sarah Schuller
Verifeid U/L listing of Solar Array install and scope of work being performed
ELE19-03736 Final10/26/201910/28/201910/28/2019 10:21:57 AMAPASS
You already looked at this. Not much to final. Phone #: ###-#### Inspection requested via web by Craig Korell
A/C final ok
ELE19-01628 Permanent Service10/28/201910/28/201910/28/2019 10:21:31 AMAPASS
Please inspect the main service Phone #: ###-#### Inspection requested via web by Darryn Coburn
AFC rating from IDPCO is 49,566 and main is 65K rated
p/s u/g n ok
ELE19-00030 Electrical Rough-In10/25/201910/28/201910/28/2019 9:37:51 AMAPASS
Showroom Fireplace Phone #: ###-#### Inspection requested via web by Bryan Atkins
Showroom fireplace and both reception desk ok to cover