ELE19-03966
| Electrical Rough-In | 10/28/2019 | 10/28/2019 | 10/28/2019 2:32:32 PM | P | PASS |
|
|
listing inspection for solar equipment; the guys will be there around 12 pm but not sooner.
PLEASE NOTE - THIS PROJECT IS AN ADDITION; so there will already be old panels on the roof. We have not started the additional panels until we get the listing inspection. Our last rough in was failed because the guys had left the site and the inspector saw that panels were already up. Give me a call if you have any questions, thanks guys Phone #: ###-#### Inspection requested via web by Ryan King Listing of panels for addition of Solar Array panels to existing system ok
|
ELE19-03053
| Final | 10/28/2019 | 10/28/2019 | 10/28/2019 2:27:27 PM | P | PASS |
|
|
Justin Metcalf ###-#### Phone #: ###-#### Inspection requested via web by Samatha Solberg Final ok-Occ card signed
|
ELE19-04095
| Electrical Rough-In | 10/28/2019 | 10/28/2019 | 10/28/2019 1:44:05 PM | P | CANC |
|
|
Phone #: ###-#### Inspection requested via web by BRS Permitting Scheduled for wrong day and will re-schedule for 10/29
|
ELE19-03683
| Electrical Rough-In | 10/28/2019 | 10/28/2019 | 10/28/2019 1:06:21 PM | P | PASS |
|
|
David Phone #: ###-#### Rough-in ok to cover
|
ELE19-04149
| Temporary Service | 10/28/2019 | 10/28/2019 | 10/28/2019 12:57:39 PM | P | PASS |
|
|
Phone #: ###-#### Inspection requested via web by Chris Berthelot t/s o/h n ok
|
ELE19-01023
| Final | 10/28/2019 | 10/28/2019 | 10/28/2019 12:33:20 PM | P | CANC |
|
|
Inspection requested via web by John Edwards Not ready
|
ELE19-04008
| Final | 10/28/2019 | 10/28/2019 | 10/28/2019 12:03:20 PM | P | PASS |
|
|
Please call Zack when you''re on your way ###-#### Final inspection for (7)outlets in ceiling and added 100amp main breaker panel interior. Phone #: ###-#### Inspection requested via web by Kendra Lanham Final ok
|
ELE19-03455
| Final | 10/26/2019 | 10/28/2019 | 10/28/2019 11:19:25 AM | A | PASS |
|
|
Service change is done. Phone #: ###-#### Inspection requested via web by Craig Korell Service change final ok
|
ELE19-03995
| Electrical Rough-In | 10/25/2019 | 10/28/2019 | 10/28/2019 11:00:06 AM | A | PASS |
|
|
Kenny Phone #: ###-#### Kitchen and bath ok to cover
|
ELE19-03947
| Electrical Rough-In | 10/25/2019 | 10/28/2019 | 10/28/2019 10:59:42 AM | A | PASS |
|
|
Phone #: ###-#### Inspection requested via web by Sarah Schuller Verifeid U/L listing of Solar Array install and scope of work being performed
|
ELE19-03736
| Final | 10/26/2019 | 10/28/2019 | 10/28/2019 10:21:57 AM | A | PASS |
|
|
You already looked at this. Not much to final. Phone #: ###-#### Inspection requested via web by Craig Korell A/C final ok
|
ELE19-01628
| Permanent Service | 10/28/2019 | 10/28/2019 | 10/28/2019 10:21:31 AM | A | PASS |
|
|
Please inspect the main service Phone #: ###-#### Inspection requested via web by Darryn Coburn AFC rating from IDPCO is 49,566 and main is 65K rated p/s u/g n ok
|
ELE19-00030
| Electrical Rough-In | 10/25/2019 | 10/28/2019 | 10/28/2019 9:37:51 AM | A | PASS |
|
|
Showroom Fireplace Phone #: ###-#### Inspection requested via web by Bryan Atkins Showroom fireplace and both reception desk ok to cover
|