ELE19-01749
| Conference | 5/13/2019 | 5/13/2019 | 5/13/2019 4:08:43 PM | P | DONE |
|
|
Malcom Phone #: ###-#### Will need to verify branch circuit in which 12g ran to areas and have 14g jumpers in between is on 15amp max breaker, Isolate grounded and grounding in both panels, re-check stapling throughout house
|
ELE19-01665
| Final | 5/13/2019 | 5/13/2019 | 5/13/2019 3:07:08 PM | P | PASS |
|
|
Please call so I know to be there Thanks Phone #: ###-#### Inspection requested via web by Eddy Udry Occ card signed Final ok
|
ELE19-01695
| Final | 5/13/2019 | 5/13/2019 | 5/13/2019 2:46:23 PM | P | PASS |
|
|
Warren-please call 45 minutes prior to meet so he can go over what was done Phone #: ###-#### Final ok
|
ELE18-02576
| Final | 5/13/2019 | 5/13/2019 | 5/13/2019 2:46:06 PM | P | PART |
|
|
Final for Building C Units 104-107, 204-207, 304-307 Contact Scott Wilson Thank you, Phone #: ###-#### Inspection requested via web by Cathy Duchek BLD C complete, partial final given unitl light poles are installed
|
ELE19-00903
| Electrical Rough-In | 5/13/2019 | 5/13/2019 | 5/13/2019 12:34:05 PM | A | PASS |
|
|
Units 203 , 204 , 205 and Elevator shaft walls Call Craig Phone #: ###-#### Inspection requested via web by Tom Betty Units as requested with elevator shaft ceiling light ok to cover
|
ELE18-04824
| Electrical Rough-In | 5/12/2019 | 5/13/2019 | 5/13/2019 11:02:02 AM | A | PASS |
|
|
Eric I Dont Know If You Need To Inspect The Pole Bases But They Are Done And The Building Inspector Said They Can Pour I Have The Photos Of The Conduit But I Have To be In Kuna At 7.00 And Should Be back To Meet Ya Thanks Dave Phone #: ###-#### Inspection requested via web by jason shifflett Light poles ok to cover
|
ELE19-01573
| Electrical Rough-In | 5/13/2019 | 5/13/2019 | 5/13/2019 10:04:18 AM | A | PASS |
|
|
Pls contact Bryce (Foreman) @ ###-#### or George (Electrician) @ ###-#### one hr prior or if you have any questions. Thank you. Inspection requested via web by Rob Maes Solar array parts all listed Scope of work ok to continue
|
ELE18-02686
| Final | 5/10/2019 | 5/13/2019 | 5/13/2019 9:50:40 AM | A | PASS |
|
|
Phone #: ###-#### Inspection requested via web by danny perrine Patio final ok
|
ELE19-01553
| Final | 5/10/2019 | 5/13/2019 | 5/13/2019 9:36:46 AM | A | PASS |
|
|
Phone #: ###-#### Inspection requested via web by BRS Permitting Final fro solar array install ok to cover
|
ELE19-01480
| Electrical Rough-In | 5/12/2019 | 5/13/2019 | 5/13/2019 9:21:28 AM | A | PASS |
|
|
Phone #: ###-#### Inspection requested via web by Rachael Moore U/G on slab to kitchen island ok to cover
|
ELE19-01481
| Electrical Rough-In | 5/12/2019 | 5/13/2019 | 5/13/2019 9:20:59 AM | A | PASS |
|
|
Phone #: ###-#### Inspection requested via web by Rachael Moore U/G for slab ok to cover to kitchen island
|
ELE19-00108
| Electrical Rough-In | 5/13/2019 | 5/13/2019 | 5/13/2019 12:00:00 AM | P | PASS |
|
|
Inspection originally scheduled on ELE19-00903. Added her per Eric Story
|
ELE19-00903
| Temporary Service | 5/13/2019 | 5/13/2019 | 5/13/2019 12:00:00 AM | P | PASS |
|
|
Inspection for temporary service originally scheduled ELE19-00108. Added her per Eric Story
|