Inspections for the day of: Monday, May 13, 2019.
Number of inspections: 13
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorEric Story
TitleELE-INSPECTOR
Phone #985-3493
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
ELE19-01749 Conference5/13/20195/13/20195/13/2019 4:08:43 PMPDONE
Malcom Phone #: ###-####
Will need to verify branch circuit in which 12g ran to areas and have 14g jumpers in between is on 15amp max breaker, Isolate grounded and grounding in both panels, re-check stapling throughout house
ELE19-01665 Final5/13/20195/13/20195/13/2019 3:07:08 PMPPASS

Please call so I know to be there
Thanks Phone #: ###-#### Inspection requested via web by Eddy Udry
Occ card signed
Final ok
ELE19-01695 Final5/13/20195/13/20195/13/2019 2:46:23 PMPPASS
Warren-please call 45 minutes prior to meet so he can go over what was done Phone #: ###-####
Final ok
ELE18-02576 Final5/13/20195/13/20195/13/2019 2:46:06 PMPPART
Final for Building C Units 104-107, 204-207, 304-307
Contact Scott Wilson
Thank you, Phone #: ###-#### Inspection requested via web by Cathy Duchek
BLD C complete, partial final given unitl light poles are installed
ELE19-00903 Electrical Rough-In5/13/20195/13/20195/13/2019 12:34:05 PMAPASS
Units 203 , 204 , 205 and Elevator shaft walls Call Craig Phone #: ###-#### Inspection requested via web by Tom Betty
Units as requested with elevator shaft ceiling light ok to cover
ELE18-04824 Electrical Rough-In5/12/20195/13/20195/13/2019 11:02:02 AMAPASS
Eric I Dont Know If You Need To Inspect The Pole Bases But They Are Done And The Building Inspector Said They Can Pour I Have The Photos Of The Conduit But I Have To be In Kuna At 7.00 And Should Be back To Meet Ya Thanks Dave Phone #: ###-#### Inspection requested via web by jason shifflett
Light poles ok to cover
ELE19-01573 Electrical Rough-In5/13/20195/13/20195/13/2019 10:04:18 AMAPASS
Pls contact Bryce (Foreman) @ ###-#### or George (Electrician) @ ###-#### one hr prior or if you have any questions. Thank you. Inspection requested via web by Rob Maes
Solar array parts all listed
Scope of work ok to continue
ELE18-02686 Final5/10/20195/13/20195/13/2019 9:50:40 AMAPASS
Phone #: ###-#### Inspection requested via web by danny perrine
Patio final ok
ELE19-01553 Final5/10/20195/13/20195/13/2019 9:36:46 AMAPASS
Phone #: ###-#### Inspection requested via web by BRS Permitting
Final fro solar array install ok to cover
ELE19-01480 Electrical Rough-In5/12/20195/13/20195/13/2019 9:21:28 AMAPASS
Phone #: ###-#### Inspection requested via web by Rachael Moore
U/G on slab to kitchen island ok to cover
ELE19-01481 Electrical Rough-In5/12/20195/13/20195/13/2019 9:20:59 AMAPASS
Phone #: ###-#### Inspection requested via web by Rachael Moore
U/G for slab ok to cover to kitchen island
ELE19-00108 Electrical Rough-In5/13/20195/13/20195/13/2019 12:00:00 AMPPASS
Inspection originally scheduled on ELE19-00903. Added her per Eric Story
ELE19-00903 Temporary Service5/13/20195/13/20195/13/2019 12:00:00 AMPPASS
Inspection for temporary service originally scheduled ELE19-00108. Added her per Eric Story