Inspections for the day of: Thursday, June 20, 2019.
Number of inspections: 7
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorEric Story
TitleELE-INSPECTOR
Phone #985-3493
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
ELE19-01858 Electrical Rough-In6/19/20196/20/20196/20/2019 3:10:31 PMPPASS
Phone #: ###-#### Inspection requested via web by Kerri Hamilton
LV wires removed from ceiling grid ok to cover
ELE19-01585 Electrical Rough-In6/20/20196/20/20196/20/2019 2:11:50 PMPPASS
We need an underground inspection, please. Bob is the site contact. Phone #: ###-#### Inspection requested via web by Stacie Tasker
Secondary conduits ok to cover
ELE19-01635 Final6/19/20196/20/20196/20/2019 11:20:08 AMAPASS
Phone #: ###-#### Inspection requested via web by Steven Ragan
Correction fixed final ok as corrections posted
ELE19-02020 Final6/18/20196/20/20196/20/2019 11:04:22 AMAFAIL
Please notify Tim of time/changes. He is traveling from Twin and would like to do around 9:00 am if possible. His number is ###-####. Thank you! Phone #: ###-#### Inspection requested via web by Amy Simms
Need BLD permit and also must have a rough-in inspection proir to install, Need material removed from roof and need approved plans on site.....
ELE18-02685 Final6/20/20196/20/20196/20/2019 10:31:31 AMAPASS
Building A Final whole building plus appliances.
Contact Scott Wilson
Thank you, Phone #: ###-#### Inspection requested via web by Cathy Duchek
Verified Install of pigtails on appliances
Occ card signed
Final ok
ELE19-01230 Final6/19/20196/20/20196/20/2019 9:41:53 AMAPASS
Lock box 3380. If you have any questions please feel free to contact Tony ###-####. Thanks!! Phone #: ###-#### Inspection requested via web by Clayton Morgan
Final ok
ELE19-02255 Rough-In Permanent Service6/19/20196/20/20196/20/2019 9:10:33 AMAPASS
Phone #: ###-#### Inspection requested via web by Tyler Ridley
Rough-in ok to cover
p/s u/g n ok