Inspections for the day of: Tuesday, September 25, 2018.
Number of inspections: 29
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorEric Strole
TitlePLM/MEC-INSPECTOR
Phone #794-7913
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
PLM18-04058 Plumbing Rough-in9/25/20189/25/20189/25/2018 3:16:06 PMPPASS
Phone #: ###-#### Inspection requested via web by Semsudin Konjuhovac
PLM18-01293 Final9/25/20189/25/20189/25/2018 2:55:39 PMPPASS
5324 enter
Job # 19640
Phone #: ###-#### Inspection requested via web by Ann Marie Reyes
MEC18-03300 Final9/24/20189/25/20189/25/2018 2:55:15 PMPPASS
AC:5324 Phone #: ###-#### Inspection requested via web by Gary Reeves
MEC18-04472 Pressure Test9/24/20189/25/20189/25/2018 2:45:29 PMPFAIL
Phone #: ###-#### Inspection requested via web by Debbie Marino-gas test fail.
MEC18-04472 Rough-in9/24/20189/25/20189/25/2018 2:45:04 PMPPASS
Phone #: ###-#### Inspection requested via web by Debbie Marino
MEC18-04554 Rough-in9/24/20189/25/20189/25/2018 2:28:40 PMPPASS
Garage code: 4211 Phone #: ###-#### Inspection requested via web by Dan Otero
MEC18-04295 Pressure Test9/25/20189/25/20189/25/2018 2:21:36 PMPPASS
Field super: Daryl Thomas Phone #: ###-#### Inspection requested via web by Lisa Whitney-20 lb gas test pass
MEC18-04295 Rough-in9/25/20189/25/20189/25/2018 2:21:14 PMPPASS
Field super: Daryl Thomas Phone #: ###-#### Inspection requested via web by Lisa Whitney
PLM17-04821 Pressure Test9/25/20189/25/20189/25/2018 1:58:29 PMPPART
This Inspection is of two different IW Tests. One is Pumped IW from the 90 Day Accumulation Room, the other is Gravity from Condensate Drains. Thank you. Phone #: ###-#### Inspection requested via web by RM Mechanical-Sections complete is marked in test result book.
PLM18-04057 Plumbing Rough-in9/25/20189/25/20189/25/2018 1:20:57 PMPPEND
Phone #: ###-#### Inspection requested via web by Kevin Smith-Rough-in ok but no inspection till plumbing and mechanical figure out who is running water heater flue.
PLM18-02459 Final9/25/20189/25/20189/25/2018 12:47:57 PMPPASS
Phone #: ###-#### Inspection requested via web by Rob Bristol
MEC18-04297 Rough-in9/24/20189/25/20189/25/2018 12:28:43 PMPPASS
Phone #: ###-#### Inspection requested via web by Gary Reeves
PLM18-02691 Groundwork9/24/20189/25/20189/25/2018 11:16:48 AMAPASS
Dave Phone #: ###-####
PLM18-03947 Final9/19/20189/25/20189/25/2018 10:40:48 AMAPASS
Please call Randy Hall prior to inspection. ###-#### Phone #: ###-#### Inspection requested via web by Mary LaFayette
PLM18-04034 Water Heater Final9/21/20189/25/20189/25/2018 9:54:35 AMAPASS
Please call Patricia when on way ###-#### Phone #: ###-#### Inspection requested via web by Kelli Morgan
PLM18-04040 Water and/or Sewer9/24/20189/25/20189/25/2018 9:37:35 AMAPART
New 2 inch water service Phone #: ###-#### Inspection requested via web by ronald gulley-OK to cover except connections.
PLM18-02624 Plumbing Rough-in9/25/20189/25/20189/25/2018 9:33:45 AMPCANC
Brad Phone #: ###-####
MEC18-04496 Pressure Test9/24/20189/25/20189/25/2018 9:05:44 AMAPEND
Call Jason with any issues @ 412.6696 Phone #: ###-#### Inspection requested via web by Dawn Kalsbeek-20 lb gas test pass.When plumbing & mechanical figure out who is installing water heater flue and flue is installed call inspection back in.
MEC18-04496 Rough-in9/24/20189/25/20189/25/2018 9:05:01 AMAPEND
Call Jason with any issues @ 412.6696 Phone #: ###-#### Inspection requested via web by Dawn Kalsbeek-Rough-in pass.When plumbing & mechanical figure out who is installing water heater flue and flue is installed call inspection back in.
PLM18-00977 Final9/18/20189/25/20189/25/2018 8:40:03 AMACANC
Please call Susan 30 min prior Phone #: ###-#### >> Inspection requested via web by Andrea Grigsby Inspection cancelled from web by: Andrea Grigsby
PLM18-04022 Groundwork9/25/20189/25/20189/25/2018 8:31:28 AMAPASS
Phone #: ###-#### Inspection requested via web by David Stephenson
MEC18-04604 Rough-in9/21/20189/25/20189/25/2018 8:31:15 AMAFAIL
CLINT ###-#### Phone #: ###-#### Inspection requested via web by Mike Almanza-Need to complete flue and install insulation sheild.
PLM18-03830 Plumbing Rough-in9/25/20189/25/20189/25/2018 8:30:41 AMPCANC
Phone #: ###-#### >> Inspection requested via web by Kevin Smith Inspection cancelled from web by: Kevin Smith
PLM17-03777 PLM-Aging Inspection9/25/20189/25/20189/25/2018 6:27:01 AM PART
No calls
MEC17-05721 Mec-Aging Inspection9/25/20189/25/20189/25/2018 6:26:22 AM PASS
MEC17-05721 DOC - Permit Finaled9/25/20189/25/20189/25/2018 6:26:13 AMAPASS
PLM17-03769 PLM-Aging Inspection9/25/20189/25/20189/25/2018 6:24:29 AM PART
No calls
MEC18-04297 Rough-in9/24/20189/25/20189/24/2018 3:45:52 PMACANC
Phone #: ###-#### >> Inspection requested via web by Gary Reeves Inspection cancelled from web by: Gary Reeves
MEC18-02937 Final9/24/20189/25/20189/24/2018 3:40:13 PMPCANC
Phone #: ###-#### >> Inspection requested via web by Gary Reeves Inspection cancelled from web by: Gary Reeves