PLM19-02634
| Groundwork | 6/24/2019 | 6/25/2019 | 6/25/2019 4:10:48 PM | P | PASS |
|
|
BELLVO CONTRACTORS: MIKE PARKER: ###-#### TENANT IMPROVEMENT GROUNDWORK Phone #: ###-#### Inspection requested via web by Chris Field
|
PLM19-02616
| Pressure Test | 6/24/2019 | 6/25/2019 | 6/25/2019 3:31:39 PM | P | PASS |
|
|
Phone #: ###-#### Inspection requested via web by Jason Brashears
|
PLM19-02639
| Sprinkler (Final) | 6/25/2019 | 6/25/2019 | 6/25/2019 2:51:38 PM | P | PART |
|
|
EMILY- as late as possible Phone #: ###-#### ok to bury backflow needs certified
|
PLM19-02632
| Final | 6/24/2019 | 6/25/2019 | 6/25/2019 2:24:59 PM | P | PASS |
|
|
INSTALLER NICK ###-#### Phone #: ###-#### Inspection requested via web by Aaron Alandt
|
PLM19-01618
| Groundwork | 6/25/2019 | 6/25/2019 | 6/25/2019 2:20:12 PM | P | PASS |
|
|
if questions call Noe @ ###-####. Phone #: ###-#### Inspection requested via web by Stacia Haumann
|
PLM19-02631
| Groundwork | 6/24/2019 | 6/25/2019 | 6/25/2019 12:01:46 PM | A | PASS |
|
|
Juan-please call 1 hr prior to meet for access Phone #: ###-####
|
PLM18-05168
| Water Heater Final | 6/24/2019 | 6/25/2019 | 6/25/2019 11:27:45 AM | A | PASS |
|
|
Please see manager onsite. They are available Monday-Friday 8am-4pm. ###-#### . Please call technician Jim Lyman for questions ###-####. Phone #: ###-#### Inspection requested via web by Scott Ferguson
|
PLM19-01618
| Water and/or Sewer | 6/24/2019 | 6/25/2019 | 6/25/2019 11:27:34 AM | A | PASS |
|
|
Water Service Line. if questions call Noe @ ###-####. Phone #: ###-#### Inspection requested via web by Stacia Haumann
|
PLM19-02641
| Water and/or Sewer | 6/24/2019 | 6/25/2019 | 6/25/2019 10:30:49 AM | A | PASS |
|
|
early am please Phone #: ###-#### Inspection requested via web by Mike Olson
|
PLM19-02641
| DOC - Permit Finaled | 6/25/2019 | 6/25/2019 | 6/25/2019 10:30:39 AM | P | PASS |
|
|
|
PLM19-02640
| Water and/or Sewer | 6/24/2019 | 6/25/2019 | 6/25/2019 10:30:22 AM | A | PASS |
|
|
early am please Phone #: ###-#### Inspection requested via web by Mike Olson
|
PLM19-02640
| DOC - Permit Finaled | 6/25/2019 | 6/25/2019 | 6/25/2019 10:30:12 AM | P | PASS |
|
|
|
PLM19-02279
| Water Softner Final | 6/20/2019 | 6/25/2019 | 6/25/2019 10:00:20 AM | A | PASS |
|
|
PLEASE CALL WHEN ON THE WAY. THANK YOU Phone #: ###-#### Inspection requested via web by Chris Field
|
PLM19-02618
| Plumbing Rough-in | 6/24/2019 | 6/25/2019 | 6/25/2019 9:27:24 AM | A | PASS |
|
|
Please call Jim 30 min prior to arrival Phone #: ###-#### Inspection requested via web by Andrea Grigsby
|
PLM19-02572
| Plumbing Rough-in | 6/24/2019 | 6/25/2019 | 6/25/2019 9:18:52 AM | A | PASS |
|
|
Per conversation with Matt Wrobel regarding vent. Thank you Phone #: ###-#### Inspection requested via web by chris mcdaniel
|
PLM19-02622
| Groundwork | 6/24/2019 | 6/25/2019 | 6/25/2019 9:10:18 AM | A | PART |
|
|
Phone #: ###-#### Inspection requested via web by Jason Gonzalez need hookup sewers and add trap primers
|
PLM19-02621
| Groundwork | 6/24/2019 | 6/25/2019 | 6/25/2019 9:10:04 AM | A | PART |
|
|
Phone #: ###-#### Inspection requested via web by Jason Gonzalez need hookup sewers and add trap primers
|
PLM19-02620
| Groundwork | 6/24/2019 | 6/25/2019 | 6/25/2019 9:09:51 AM | A | PART |
|
|
Phone #: ###-#### Inspection requested via web by Jason Gonzalez need hookup sewers and add trap primers
|
PLM17-05049
| PLM-Aging Inspection | 6/25/2019 | 6/25/2019 | 6/25/2019 8:12:03 AM | | PART |
|
|
wip
|
PLM18-04152
| PLM-Aging Inspection | 6/25/2019 | 6/25/2019 | 6/25/2019 8:11:20 AM | | PART |
|
|
no calls
|
PLM18-04140
| PLM-Aging Inspection | 6/25/2019 | 6/25/2019 | 6/25/2019 8:10:46 AM | | PART |
|
|
wip
|
PLM18-04158
| PLM-Aging Inspection | 6/25/2019 | 6/25/2019 | 6/25/2019 8:09:59 AM | | PART |
|
|
no calls
|
PLM19-02616
| Pressure Test | 6/24/2019 | 6/25/2019 | 6/24/2019 6:42:56 PM | A | CANC |
|
|
Phone #: ###-#### >> Inspection requested via web by Jason Brashears Inspection cancelled from web by: Jason Brashears
|