BLD13-00161
| FIRE-Sprinkler Rough-in | 3/25/2013 | 3/25/2013 | 3/25/2013 5:25:16 PM | P | PART |
|
|
Fire sprinkler work above the new grid ceilings okayed for cover.
|
BLD12-03139
| FIRE-Sprinkler Rough-in | 3/25/2013 | 3/25/2013 | 3/25/2013 5:21:36 PM | P | PART |
|
|
Okay to cover fire sprinkler system modifications at the phase one new ceilings.
|
FIR13-00131
| INSP-Final Inspection | 3/25/2013 | 3/25/2013 | 3/25/2013 5:19:49 PM | P | PART |
|
|
|
FIR12-00433
| INSP-Alarm Testing | 3/21/2013 | 3/25/2013 | 3/25/2013 5:18:55 PM | P | NR |
|
|
|
FIR08-00368
| FIR-Aging Inspection | 3/25/2013 | 3/25/2013 | 3/25/2013 1:14:47 PM | | DONE |
|
|
Project incomplete. Spoke with Noah- the general contractor on site regarding completion dates.
|
FIR08-00387
| FIR-Aging Inspection | 3/25/2013 | 3/25/2013 | 3/25/2013 1:13:50 PM | | DONE |
|
|
Project incomplete. Spoke with Noah- the general contractor on site regarding completion dates.
|
FIR08-00825
| FIR-Aging Inspection | 3/25/2013 | 3/25/2013 | 3/25/2013 1:11:55 PM | | PEND |
|
|
Site work incomplete
|
FIR13-00121
| INSP-Final Inspection | 3/22/2013 | 3/25/2013 | 3/25/2013 1:06:37 PM | A | PART |
|
|
Scope of fire sprinkler work completed
|
BLD12-01772
| FIRE-Conference | 3/19/2013 | 3/25/2013 | 3/25/2013 1:05:21 PM | A | DONE |
|
|
Regarding conditions for fire life safety approvals, scope of work, schedule, etc.
|
BLD13-00609
| FIRE-Conference | 3/22/2013 | 3/25/2013 | 3/25/2013 1:00:33 PM | A | DONE |
|
|
Regarding C/N items
|
BLD12-02737
| FIRE-Conference | 3/25/2013 | 3/25/2013 | 3/25/2013 12:57:26 PM | A | DONE |
|
|
Conversation with contractor on site regarding knox box, new hydrant, review notes, IFC ch. 22 and 34, project related fire alarm permit, etc.
|