FIR14-00281
| INSP-Conference | 8/19/2014 | 8/19/2014 | 8/19/2014 4:51:27 PM | P | DONE |
|
|
Regarding inspection schedule
|
FIR13-00663
| INSP-Final Inspection | 8/19/2014 | 8/19/2014 | 8/19/2014 4:50:48 PM | P | PASS |
|
|
Scope of work completed. Fire sprinkler permit finaled, inspection passed.
|
FIR14-00121
| INSP-Final Inspection | 8/19/2014 | 8/19/2014 | 8/19/2014 4:49:34 PM | P | PASS |
|
|
Walkthrough passed. Fire sprinkler permit finaled.
|
FIR14-00372
| INSP-Conference | 8/19/2014 | 8/19/2014 | 8/19/2014 4:48:25 PM | P | DONE |
|
|
Regarding project inspection and testing schedule.
|
FIR14-00345
| INSP-Sprinkler Rough-in | 8/19/2014 | 8/19/2014 | 8/19/2014 4:47:24 PM | P | PART |
|
|
Okay to cover overhead fire sprinkler work at areas marked and dated on plans. Five heads at the north hall will need relocated due to cable tray obstructions, the break area south end is not yet finished- discussed light fixture obstructions at this area.
|
FIR14-00231
| INSP-Final Inspection | 8/19/2014 | 8/19/2014 | 8/19/2014 2:13:43 PM | P | PASS |
|
|
Record drawings accepted. Fire sprinkler work passed final inspection. Permit finaled.
|
FIR14-00130
| INSP-Final Inspection | 8/19/2014 | 8/19/2014 | 8/19/2014 2:09:49 PM | P | PASS |
|
|
Verified plan modification, final walkthrough passed inspection. Permit finaled.
|
FIR14-00261
| INSP-Sprinkler Rough-in/Hydro | 8/19/2014 | 8/19/2014 | 8/19/2014 1:50:20 PM | A | PART |
|
|
Inspection for standpipe completed. Need to provide seismic clearance at floor landings, install guage at the top level.
|
BLD14-01981
| FIRE-Sprinkler Rough-in | 8/19/2014 | 8/19/2014 | 8/19/2014 1:40:34 PM | A | PART |
|
|
Fire sprinkler modifications okayed for cover.
|
FIR14-00325
| INSP-Sprinkler Rough-in/Hydro | 8/18/2014 | 8/19/2014 | 8/19/2014 1:37:43 PM | A | PART |
|
|
UG fire supply line passed hydrostatic testing.
|