Inspections for the day of: Thursday, June 28, 2018.
Number of inspections: 7
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorChad Schwendiman
TitleMEC-INSPECTOR
Phone #780-9549
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
MEC18-02478 Rough-in6/28/20186/28/20186/28/2018 4:38:00 PMPFAIL
rough in inspection needed prior to insulation of duct work.
please call fred with any questions Phone #: ###-#### Inspection requested via web by Nick Drake - No access
MEC18-02966 Pressure Test6/27/20186/28/20186/28/2018 2:46:38 PMPFAIL
Just need to have a final inspection done. Phone #: ###-#### Inspection requested via web by Trenton Kemp - Need to use 30lb gauge with a minimum of 20lbs in it.
MEC17-04433 Rough-in6/27/20186/28/20186/28/2018 1:40:19 PMACANC
Travis--as early as possible Phone #: ###-####
MEC17-04433 Final6/28/20186/28/20186/28/2018 1:40:11 PMPPART
Travis--as early as possible Phone #: ###-#### - Phase 1 TCO okay. There are Deficiencies in the air balance report that need to be corrected proir to signing off on CO
MEC18-01938 Rough-in6/27/20186/28/20186/28/2018 10:43:47 AMAPART
Rough in ; Francisco is your contact. Thank you! Phone #: ###-#### Inspection requested via web by Kim Adams - Okay to insulate duct work
MEC18-01937 Rough-in6/27/20186/28/20186/28/2018 10:42:41 AMAPART
Rough In ; Francisco is your contact. thank you! Phone #: ###-#### Inspection requested via web by Kim Adams - Okay to insulate duct work
MEC18-02885 Rough-in6/27/20186/28/20186/28/2018 10:18:38 AMAPASS
Rough In for Bathroom - Please Call Rob with any questions ###-#### Phone #: ###-#### Inspection requested via web by Bailey Esposito