MIS19-00044
| MIS-Aging Inspection | 1/9/2020 | 1/9/2020 | 1/10/2020 5:09:42 PM | | DONE |
|
|
|
MIS19-00036
| MIS-Aging Inspection | 1/9/2020 | 1/9/2020 | 1/10/2020 5:08:25 PM | | DONE |
|
|
|
BLD18-02193
| BLD-Final | 1/7/2020 | 1/9/2020 | 1/10/2020 11:02:27 AM | A | PASS |
|
|
PJ Smith// status of public works pass
|
BLD18-00945
| BLD-Final | 1/9/2020 | 1/9/2020 | 1/9/2020 3:20:19 PM | P | NR |
|
|
Phone #: ###-#### Inspection requested via web by Ron Goff// need letters from the engineer
|
MIS20-00007
| BLD-Conference | 1/8/2020 | 1/9/2020 | 1/9/2020 3:19:07 PM | P | PEND |
|
|
Caller concerned about structural integrity of the building. Large hole in foundation, does not believe roof work was permitted prior. Phone #: ###-####// status review
|
MIS20-00005
| BLD-Conference | 1/8/2020 | 1/9/2020 | 1/9/2020 3:18:53 PM | A | PEND |
|
|
status review Phone #: ###-####
|
BLD19-04911
| BLD-Final | 1/7/2020 | 1/9/2020 | 1/9/2020 3:02:28 PM | P | DONE |
|
|
call ahead Don - solar panels Phone #: ###-####
|
BLD19-04911
| DOC - Permit Finaled | 1/9/2020 | 1/9/2020 | 1/9/2020 3:01:44 PM | P | PASS |
|
|
done
|
BLD20-00084
| BLD-Framing/Rough-in | 1/9/2020 | 1/9/2020 | 1/9/2020 2:38:06 PM | P | PART |
|
|
window // Joshua Phone #: ###-####// frame ok pending plumbing pass
|
BLD19-04632
| BLD-Footing | 1/9/2020 | 1/9/2020 | 1/9/2020 2:13:20 PM | P | PART |
|
|
bill Phone #: ###-####// work in progress,, ok
|
BLD19-01685
| BLD-Energy code compliance | 1/9/2020 | 1/9/2020 | 1/9/2020 2:03:55 PM | P | PASS |
|
|
Phone #: ###-#### Inspection requested via web by James Jackson
|
BLD18-04149
| BLD-Final | 1/9/2020 | 1/9/2020 | 1/9/2020 1:18:22 PM | P | PASS |
|
|
BOB Phone #: ###-####// c of o issued
|
BLD18-04149
| DOC - Permit Finaled | 1/9/2020 | 1/9/2020 | 1/9/2020 1:18:07 PM | P | PASS |
|
|
|
BLD18-04149
| BLD-Blower Door Test Results | 1/9/2020 | 1/9/2020 | 1/9/2020 1:16:28 PM | P | PASS |
|
|
BOB Phone #: ###-#### // 3.0
|
BLD19-02691
| BLD-Framing/Rough-in | 1/8/2020 | 1/9/2020 | 1/9/2020 11:39:23 AM | A | PART |
|
|
Phone #: ###-#### Inspection requested via web by Josh Strasser// walls ok after bracing as needed
|
BLD19-01828
| BLD-Energy code compliance | 1/8/2020 | 1/9/2020 | 1/9/2020 10:59:47 AM | A | PART |
|
|
Insulation in 1st, 2nd, ; 3rd floor corridors. Phone #: ###-#### Inspection requested via web by Michael Zaccheo,, ok to cover ceilings to do trades under
|
BLD19-02620
| BLD-Wall cover | 1/8/2020 | 1/9/2020 | 1/9/2020 10:15:49 AM | A | PASS |
|
|
Party wall truss GWB shear inspection. Thanks, Phone #: ###-#### Inspection requested via web by Nic Van Diepen
|
BLD19-01685
| BLD-Energy code compliance | 1/8/2020 | 1/9/2020 | 1/9/2020 9:33:52 AM | A | PART |
|
|
Phone #: ###-#### Inspection requested via web by James Jackson// met w/ owner, contractor and insulation contractor to go over minor issues,, will re-inspect in pm
|
BLD19-01828
| BLD-Energy code compliance | 1/8/2020 | 1/9/2020 | 1/8/2020 4:55:10 PM | P | CANC |
|
|
Corridor ceiling insulation on 1st, 2nd, & 3rd floors. Phone #: ###-#### >> Inspection requested via web by Michael Zaccheo Inspection cancelled from web by: Michael Zaccheo
|