BLD18-04250
| BLD-Aging Inspection | 10/15/2019 | 10/15/2019 | 10/21/2019 11:19:44 AM | | PEND |
|
|
|
BLD18-04325
| BLD-Aging Inspection | 10/15/2019 | 10/15/2019 | 10/21/2019 11:18:15 AM | | PEND |
|
|
|
MIS19-00333
| BLD-Conference | 10/11/2019 | 10/15/2019 | 10/16/2019 4:17:03 PM | P | PEND |
|
|
status review,, c/n posted to follow through with the permit
|
BLD19-02593
| BLD-Wall cover | 10/15/2019 | 10/15/2019 | 10/15/2019 4:57:27 PM | P | PASS |
|
|
Exterior soffit 1hr rating sheetrock periodic inspection. Please call Nic a half hour before inspection. Thanks, Phone #: ###-#### Inspection requested via web by Nic Van Diepen// east soffit has 2 layers,, ok
|
BLD18-04214
| BLD-Framing/Rough-in | 10/14/2019 | 10/15/2019 | 10/15/2019 4:32:47 PM | P | FAIL |
|
|
Dan Phone #: ###-#### Inspection requested via web by Daniel Appel,, c/n posted,, needs fireplace pass, seal package, plans, truss engineering prior to frame
|
BLD19-03973
| BLD-Conference | 10/15/2019 | 10/15/2019 | 10/15/2019 4:11:44 PM | P | PASS |
|
|
Phone #: ###-#### Inspection requested via web by Jeff Ware,, stair conf.,, ok
|
BLD19-00036
| BLD-Foundation | 10/15/2019 | 10/15/2019 | 10/15/2019 2:47:55 PM | P | PART |
|
|
Phone #: ###-#### Inspection requested via web by Trent Howie,, basement walls ok to pour when ready
|
BLD19-03053
| BLD-Conference | 10/15/2019 | 10/15/2019 | 10/15/2019 2:47:07 PM | P | DONE |
|
|
Ryan Phone #: ###-####,, A-35s on blocks ok
|
BLD19-03615
| DOC - Permit Finaled | 10/15/2019 | 10/15/2019 | 10/15/2019 2:45:18 PM | P | PASS |
|
|
historical not needed per T.V.
|
BLD19-03096
| BLD-Final | 10/14/2019 | 10/15/2019 | 10/15/2019 2:44:13 PM | P | DONE |
|
|
Phone #: ###-#### Inspection requested via web by Kilee Russell
|
BLD19-03096
| DOC - Permit Finaled | 10/15/2019 | 10/15/2019 | 10/15/2019 2:04:26 PM | P | PASS |
|
|
done
|
BLD18-02746
| BLD-Framing/Rough-in | 10/14/2019 | 10/15/2019 | 10/15/2019 1:58:45 PM | A | PASS |
|
|
Josh Phone #: ###-####,, ok to insulate
|
BLD19-02292
| DOC - Permit Finaled | 10/15/2019 | 10/15/2019 | 10/15/2019 1:31:55 PM | P | PASS |
|
|
|
BLD19-03377
| BLD-Footing | 10/14/2019 | 10/15/2019 | 10/15/2019 12:33:33 PM | A | PART |
|
|
Footing will be ready for inspection at 11 am Concrete schedule for 1 pm Phone #: ###-#### Inspection requested via web by Edgar Sanchez.. work in progress,, ok to pour when ready
|
BLD19-02225
| BLD-Ceiling Grid Inspection | 10/14/2019 | 10/15/2019 | 10/15/2019 12:15:18 PM | A | PART |
|
|
Dale Phone #: ###-####, existing grid, , ok after trades,,
|
BLD19-02311
| BLD-Framing/Rough-in | 10/14/2019 | 10/15/2019 | 10/15/2019 11:14:58 AM | A | PART |
|
|
Dan Phone #: ###-####,, ok to insulate after minor corrections
|
BLD19-02603
| BLD-Framing/Rough-in | 10/14/2019 | 10/15/2019 | 10/15/2019 11:13:06 AM | A | PASS |
|
|
Dave Phone #: ###-####,, grid ok
|
BLD19-02591
| BLD-Energy code compliance | 10/14/2019 | 10/15/2019 | 10/15/2019 9:45:47 AM | A | PASS |
|
|
Exterior wall insulation inspection. Please call Nic a half hour before inspection. Thanks, Phone #: ###-#### Inspection requested via web by Nic Van Diepen
|
BLD19-02590
| BLD-Energy code compliance | 10/14/2019 | 10/15/2019 | 10/15/2019 9:45:19 AM | A | PASS |
|
|
Exterior wall insulation inspection. Please call Nic a half hour before inspection. Thanks, Phone #: ###-#### Inspection requested via web by Nic Van Diepen
|
BLD19-02593
| BLD-Energy code compliance | 10/14/2019 | 10/15/2019 | 10/15/2019 9:45:06 AM | A | PASS |
|
|
Wall insulation inspection. Thanks, Phone #: ###-#### Inspection requested via web by Nic Van Diepen
|
BLD19-02592
| BLD-Energy code compliance | 10/14/2019 | 10/15/2019 | 10/15/2019 9:44:34 AM | A | PASS |
|
|
Wall insulation inspection. Thanks, Phone #: ###-#### Inspection requested via web by Nic Van Diepen
|