Inspections for the day of: Monday, November 19, 2018.
Number of inspections: 23
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorTony Young
TitleBLD-COM/RES INSPECTOR
Phone #794-9462
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
BLD18-01614 BLD-Blower Door Test Results11/16/201811/19/201811/20/2018 1:33:13 PMADONE
Todd Phone #: ###-####/// 4.1
MIS17-00379 MIS-Aging Inspection11/19/201811/19/201811/20/2018 12:54:16 PM PEND
MIS18-00431 BLD-Conference11/19/201811/19/201811/20/2018 8:02:39 AMPNH
complaint doing major TI work at building. Possible started work on BLD18-00133 that is not issued yet./// status review
BLD18-01614 BLD-Final11/16/201811/19/201811/19/2018 3:35:53 PMAPASS
Todd Phone #: ###-####,, ok after blower door results
BLD18-03353 BLD-Wall Bracing11/19/201811/19/201811/19/2018 3:33:11 PMPPART
Dan Phone #: ###-#### Inspection requested via web by Daniel Appel,, exterior ok,, will need interior also
BLD18-03211 BLD-Framing/Rough-in11/19/201811/19/201811/19/2018 3:26:56 PMPPASS
Phone #: ###-#### Inspection requested via web by Kirsten Dallmann,, walls ok after bracing better
BLD18-00746 BLD-Blower Door Test Results11/19/201811/19/201811/19/2018 3:06:01 PMPFAIL
6.08
MIS18-00436 BLD-Conference11/16/201811/19/201811/19/2018 3:02:40 PMPPEND
structural work w/o permits// status
BLD18-03874 BLD-Footing11/16/201811/19/201811/19/2018 2:58:03 PMPPART
Rob Phone #: ###-####
BLD18-03310 BLD-Wall cover11/19/201811/19/201811/19/2018 2:56:33 PMPPASS
Gary Phone #: ###-####,, exterior ok
BLD18-00746 BLD-Final11/19/201811/19/201811/19/2018 2:54:30 PMPPASS
Phone #: ###-#### Inspection requested via web by Braxton Hansen
BLD18-00746 DOC - Permit Finaled11/19/201811/19/201811/19/2018 2:53:35 PMPPASS
c of o issued
BLD18-03184 BLD-Wall Bracing11/16/201811/19/201811/19/2018 12:59:27 PMAPASS
Chris Phone #: ###-####
BLD18-01845 BLD-Wall Bracing11/18/201811/19/201811/19/2018 12:47:10 PMAPASS
Phone #: ###-#### Inspection requested via web by James Jackson
BLD18-02153 BLD-Conference11/14/201811/19/201811/19/2018 12:35:30 PMAPASS
Thomas Phone #: ###-####,, owners are taking over the permit as self contractors
BLD18-02185 BLD-Foundation11/16/201811/19/201811/19/2018 11:59:45 AMAPASS
retaining wall - Kevin Phone #: ###-####,, 2nd lower wall ok
BLD18-00626 BLD-Final11/16/201811/19/201811/19/2018 11:54:15 AMAPASS
ok now to final
BLD18-00626 DOC - Permit Finaled11/19/201811/19/201811/19/2018 11:53:54 AMPPASS
BLD18-03353 BLD-Wall Bracing11/16/201811/19/201811/19/2018 11:34:16 AMANR
Dan Phone #: ###-#### Inspection requested via web by Daniel Appel,, nail per plan, I will check back in the pm
BLD18-02497 BLD-Footing11/15/201811/19/201811/19/2018 11:16:02 AMAPART
As early as possible Phone #: 2088502262 >> Inspection requested via mobile web by Tim,, special inspection required,, looked at the plans,, south and east footings,, work in progress
BLD17-04135 DOC - Permit Expired10/4/201811/19/201811/19/2018 8:53:34 AMAPASS
BLD17-01787 DOC - Permit Expired10/4/201811/19/201811/19/2018 8:52:50 AMAPASS
BLD18-03249 BLD-Footing11/17/201811/19/201811/17/2018 10:11:05 AMACANC
As early as possible Phone #: 2088616923 >> Inspection requested via mobile web by Fabian Noel Inspection cancelled via mobile web on Saturday, November 17, 2018.