Inspections for the day of: Monday, November 4, 2019.
Number of inspections: 20
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorTony Young
TitleBLD-COM/RES INSPECTOR
Phone #794-9462
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
BLD18-02234 BLD-Aging Inspection11/4/201911/4/201911/6/2019 8:19:09 AM PEND
BLD19-02619 BLD-Footing11/4/201911/4/201911/6/2019 8:17:06 AMPNR
Chris Phone #: ###-####
BLD19-01828 BLD-Foundation11/4/201911/4/201911/4/2019 4:23:09 PMPPEND
CMU rebar on north stair tower ; elevator shaft. Grout pour is scheduled for 1:45 pm Phone #: ###-#### Inspection requested via web by Michael Zaccheo// pending Special inspection report
BLD19-01777 BLD-Other11/4/201911/4/201911/4/2019 4:09:49 PMPPASS
Tom-- inspection for soffit and facia Phone #: ###-####/// 2 layers 5/8 " sheet rock on the facia and soffits ok
BLD19-04126 BLD-Framing/Rough-in11/4/201911/4/201911/4/2019 4:04:10 PMPPASS
call 1 hour for access- Paul Phone #: ###-####,, ok to cover
BLD19-04085 BLD-Final10/31/201911/4/201911/4/2019 3:42:33 PMPNR
Mierins Rozentals is the on site contact Phone #: ###-#### Inspection requested via web by BRS Permitting,, needs electrical final passed 1st
BLD19-03142 BLD-Final10/31/201911/4/201911/4/2019 3:36:07 PMAPASS
Final on Vanilla Shell. Building is locked until 8am. Phone #: ###-#### Inspection requested via web by Kirsten Dallmann
BLD19-04042 BLD-Footing11/1/201911/4/201911/4/2019 3:30:58 PMPPASS
Inspection requested 11/4, 1PM - 2PM if at all possible please. Phone #: ###-#### Inspection requested via web by David Dexter,, post footings ok
BLD19-03518 BLD-Energy code compliance11/4/201911/4/201911/4/2019 2:27:11 PMPPASS
existing insulation in wall south bathroom wall. Inspection for cover Phone #: ###-#### Inspection requested via web by Andrew Connell// ok after sealing holes in plates and fireblocking double wall areas
BLD19-03518 BLD-Framing/Rough-in11/4/201911/4/201911/4/2019 2:26:03 PMPPASS
Framing in bathroom for new tub Phone #: ###-#### Inspection requested via web by Andrew Connell
BLD19-01163 BLD-Conference11/4/201911/4/201911/4/2019 2:22:18 PMPPART
Dillon Phone #: ###-####,, ok to do the base layer of foam in the attic
BLD18-04065 BLD-Final11/4/201911/4/201911/4/2019 1:46:13 PMPNR
Call on the way // michael Phone #: ###-####// needs historical and hand/guard rails to meet code.. address
BLD19-02125 BLD-Foundation10/31/201911/4/201911/4/2019 1:25:56 PMAPART
Phone #: ###-#### Inspection requested via web by Ken Litzinger,, work in progress
BLD19-03446 BLD-Foundation11/1/201911/4/201911/4/2019 12:21:04 PMAPART
edguar Phone #: ###-####,, work in progress,, ok
BLD19-00043 BLD-Conference10/31/201911/4/201911/4/2019 11:58:27 AMAPART
progress inspection before installing plywood.
Phone #: ###-#### Inspection requested via web by Micah Deffries// roof frame ?s,, ok to continue,, just justify
BLD19-01944 BLD-Final11/1/201911/4/201911/4/2019 11:32:06 AMAPASS
call for access // Kevin Phone #: ###-####
BLD19-01944 DOC - Permit Finaled11/4/201911/4/201911/4/2019 11:31:58 AMPPASS
BLD19-01000 BLD-Final11/1/201911/4/201911/4/2019 10:34:00 AMAPASS
Mark Dagle Phone #: ###-####
BLD19-01000 DOC - Permit Finaled11/4/201911/4/201911/4/2019 10:33:44 AMPPASS
BLD19-01000 BLD-Blower Door Test Results11/4/201911/4/201911/4/2019 10:33:30 AMPDONE
Mark Dagle Phone #: ###-####/// 4.32