Inspections for the day of: Monday, February 3, 2020.
Number of inspections: 17
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorTony Young
TitleBLD-COM/RES INSPECTOR
Phone #794-9462
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
BLD19-00893 BLD-Aging Inspection2/3/20202/3/20202/4/2020 11:14:35 AM PEND
BLD19-03482 BLD-Conference2/3/20202/3/20202/3/2020 4:08:27 PMPPART
Ron Phone #: ###-####,, ?s on walls,,
BLD18-04243 BLD-Framing/Rough-in2/3/20202/3/20202/3/2020 3:25:15 PMPPART
Framing inspection for 1 side cover at 2nd floor interior walls. Phone #: ###-#### Inspection requested via web by Jared Waggoner,, interior wall ok to cover one side from 10 foot up to deck pending trades
BLD18-04369 BLD-Framing/Rough-in2/3/20202/3/20202/3/2020 3:23:57 PMPPART
Framing inspection for 1 side at interior 2nd floor walls Phone #: ###-#### Inspection requested via web by Jared Waggoner/// ok to one side from 10' up pending trades
BLD19-04734 BLD-Framing/Rough-in2/3/20202/3/20202/3/2020 3:00:18 PMPNR
stem wall // Willy Phone #: ###-####// not a frame,, foundation ok
BLD19-03735 BLD-Final1/29/20202/3/20202/3/2020 2:50:42 PMPPASS
llir Phone #: ###-####
BLD19-03735 DOC - Permit Finaled2/3/20202/3/20202/3/2020 2:50:28 PMPPASS
BLD19-02849 BLD-Energy code compliance1/31/20202/3/20202/3/2020 2:31:07 PMPPASS
Dennis Phone #: ###-####
MIS20-00033 Set Bond Amount2/3/20202/3/20202/3/2020 2:06:31 PMPPASS
set bond amount for existing garage only/// recomend a $2500 bond
BLD19-00355 BLD-Final2/3/20202/3/20202/3/2020 1:58:40 PMPPASS
Call to meet // Manny Phone #: ###-####
BLD19-00355 DOC - Permit Finaled2/3/20202/3/20202/3/2020 1:58:18 PMPPASS
BLD19-03446 BLD-Framing/Rough-in1/31/20202/3/20202/3/2020 11:54:39 AMAPASS
Final Framing Inspection Phone #: ###-#### Inspection requested via web by Oleksiy Yanchuk// ok to insulate
BLD19-04535 BLD-Footing1/31/20202/3/20202/3/2020 11:27:19 AMANR
pour at 12 // Dave Phone #: ###-####,, needs soils approval,, ground is frozen
BLD16-04138 BLD-Final1/31/20202/3/20202/3/2020 10:41:31 AMANR
Keith Phone #: ###-#### needs trades to final 1st
BLD19-03895 BLD-Foundation2/2/20202/3/20202/3/2020 10:38:12 AMADONE
Foundation wall inspection. Thank you! Phone #: ###-#### Inspection requested via web by Craig Hammett// already poured
BLD19-03896 BLD-Foundation2/2/20202/3/20202/3/2020 10:37:19 AMAPASS
Foundation wall inspection. Thank you! Phone #: ###-#### Inspection requested via web by Craig Hammett
BLD19-00352 DOC - Permit Expired12/19/20192/3/20202/3/2020 10:13:25 AMAPASS