Inspections for the day of: Tuesday, May 22, 2018.
Number of inspections: 19
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorTony Young
TitleBLD-COM/RES INSPECTOR
Phone #794-9462
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
MIS18-00058 MIS-Aging Inspection5/22/20185/22/20185/25/2018 8:54:49 AM PASS
BLD17-02409 BLD-Aging Inspection5/22/20185/22/20185/25/2018 8:54:32 AM PEND
MIS18-00057 MIS-Aging Inspection5/22/20185/22/20185/25/2018 8:54:15 AM PEND
BLD18-00057 BLD-Aging Inspection5/22/20185/22/20185/25/2018 8:53:37 AM PEND
MIS18-00185 BLD-Conference5/18/20185/22/20185/23/2018 7:10:11 AMPPEND
Please call // Lori CDHD or ###-#### Phone #: ###-####// follow up
BLD17-04468 BLD-Conference5/22/20185/22/20185/23/2018 7:04:45 AMPPASS
Jayson,, frame fix; Phone #: ###-####
BLD18-01449 BLD-Energy code compliance5/22/20185/22/20185/23/2018 7:04:34 AMPPASS
Phone #: ###-#### Inspection requested via web by Brandon Wiley
BLD18-01483 BLD-Footing5/21/20185/22/20185/22/2018 3:14:19 PMPPART
Phone #: 2089495359 >> Inspection requested via mobile web by Ricardo Lira,, work in progress
BLD17-01609 BLD-Foundation5/22/20185/22/20185/22/2018 2:54:56 PMPPART
Inspection for block walls for grading. Inspection prior to pour of concrete in blocks. Thank you, steve Phone #: ###-#### Inspection requested via web by steve hanson,, work ion progress,, talked w/ masons helper
BLD17-01609 BLD-Other5/22/20185/22/20185/22/2018 1:05:16 PMAPART
Inspection for block walls for grading. Inspection prior to pour of concrete in blocks. Thank you, steve Phone #: ###-#### Inspection requested via web by steve hanson/// needs to finish rebar verticals and tie in to existing wall
BLD17-02288 BLD-Conference5/21/20185/22/20185/22/2018 1:02:31 PMAPART
I would like a consult on my partially done framing for my basement bathroom renovation. Thanks Phone #: ###-#### Inspection requested via web by David Snyderman,, walk through on framing,, ok so far on the bathroom area
BLD17-03576 BLD-Conference5/21/20185/22/20185/22/2018 1:00:36 PMAPART
Ryan, 1212; Phone #: ###-####,, complicated job,, needs soils report,, etc
BLD18-00630 BLD-Energy code compliance5/21/20185/22/20185/22/2018 11:46:34 AMAPASS
Phone #: ###-#### Inspection requested via web by Ken Litzinger
BLD18-01462 BLD-Final5/21/20185/22/20185/22/2018 11:37:55 AMAPASS
Pls contact Bryce (Foreman) @ ###-#### or George (Electrician) @ ###-#### one hr prior or if you have any questions. Thank you. Inspection requested via web by Rob Maes
BLD18-01462 DOC - Permit Finaled5/22/20185/22/20185/22/2018 11:37:44 AMPPASS
done
BLD18-01449 BLD-Framing/Rough-in5/21/20185/22/20185/22/2018 11:36:20 AMAPASS
Phone #: ###-#### Inspection requested via web by Brandon Wiley
BLD18-00701 BLD-Energy code compliance5/21/20185/22/20185/22/2018 11:24:09 AMAPASS
Phone #: ###-#### Inspection requested via web by Jaysen Porter
BLD18-00701 BLD-Framing/Rough-in5/21/20185/22/20185/22/2018 11:23:58 AMAPASS
Phone #: ###-#### Inspection requested via web by Jaysen Porter
BLD18-01520 BLD-Conference5/21/20185/22/20185/22/2018 12:00:00 AMACANC
Dusty-please call ahead Phone #: ###-####