Inspections for the day of: Wednesday, July 11, 2018.
Number of inspections: 23
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorTony Young
TitleBLD-COM/RES INSPECTOR
Phone #794-9462
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
BLD17-02747 BLD-Aging Inspection7/11/20187/11/20187/12/2018 8:39:08 AM PEND
BLD18-01936 BLD-Footing7/10/20187/11/20187/11/2018 5:12:43 PMPPEND
This footing inspection can be done in the PM tomorrow. Jimmy will be the inspector and his cell number is ###-####. Thanks. Phone #: ###-#### Inspection requested via web by rich prasch,, ok pending soils approval
BLD18-00820 BLD-Wall Bracing7/10/20187/11/20187/11/2018 5:12:05 PMPPASS
Maita-would like as late as possible Phone #: ###-####
BLD18-01605 BLD-Wall Bracing7/10/20187/11/20187/11/2018 5:10:40 PMPDEFR
shear // Corey Phone #: ###-####,, power line is down,, no access,, re-scheduled to am
BLD18-01873 BLD-Conference7/10/20187/11/20187/11/2018 4:39:35 PMAPASS
The framing by the beam isn''t the block that you requested, it didn''t secure firmly. They created a 2x4 catwalk support. Please inspect and provide feedback to approval at framing. Please see me, Scott, John or Luke for more info. Phone #: ###-#### Inspection requested via web by Marianne Morrison,, walk through,, ok
BLD16-01870 BLD-Footing7/11/20187/11/20187/11/2018 4:00:38 PMPDONE
Pat Phone #: ###-####,, was redone,, poured,, looks ok
BLD16-01870 DOC - Permit Finaled7/11/20187/11/20187/11/2018 4:00:09 PMPPASS
BLD16-01870 BLD-Framing/Rough-in7/11/20187/11/20187/11/2018 3:59:52 PMPPASS
Pat Phone #: ###-####
BLD18-01717 BLD-Footing7/11/20187/11/20187/11/2018 3:45:58 PMPPART
As early as possible Phone #: 2088708888 >> Inspection requested via mobile web by Wes
BLD18-02396 BLD-Foundation7/11/20187/11/20187/11/2018 3:12:46 PMPPART
Matt Phone #: ###-####,, new added to existing point load footings on front,, 5 total
BLD18-01142 BLD-Energy code compliance7/11/20187/11/20187/11/2018 2:43:29 PMPPASS
Located at rear of property in alley. If arriving after 4pm please let me know so I can stay on site.
Chris Phone #: ###-#### Inspection requested via web by Chris Planinshek
BLD17-01802 BLD-Framing/Rough-in7/10/20187/11/20187/11/2018 2:26:45 PMPPEND
For Stage Expansion framing. Phone #: ###-#### Inspection requested via web by Scott Henderson,, needs trades 1st
BLD16-01529 BLD-Final7/11/20187/11/20187/11/2018 2:18:10 PMPNR
Jerry Phone #: ###-####,, needs historical 1st,, no inspection made
BLD18-01860 BLD-Footing7/11/20187/11/20187/11/2018 2:15:08 PMPPASS
Subgrade inspection was completed and sent email letter to Melissa. Anytime in the PM today, if possible, will be fine. Thanks. Phone #: ###-#### Inspection requested via web by rich prasch
BLD18-00472 BLD-Foundation7/10/20187/11/20187/11/2018 2:14:35 PMAPART
Waylon Phone #: ###-####,, east and east side of the north wall ok to shoot
BLD18-02307 BLD-Wall cover7/8/20187/11/20187/11/2018 12:41:08 PMAPASS
Phone #: ###-#### Inspection requested via web by Timothy Gammill,, frame ok,, ok to insulate, need to verify seal package
BLD17-04199 BLD-Final7/10/20187/11/20187/11/2018 12:40:04 PMAPART
Mark Phone #: ###-####,, ok except needs historical
BLD18-01077 BLD-Framing/Rough-in7/10/20187/11/20187/11/2018 12:11:01 PMAPASS
Phone #: ###-#### Inspection requested via web by Andrew Schneider
BLD17-03854 BLD-Final7/10/20187/11/20187/11/2018 11:55:40 AMADEFR
Dale Phone #: ###-####,, to am 7/12
BLD18-01717 BLD-Footing7/10/20187/11/20187/11/2018 11:44:48 AMANR
As early as possible Phone #: 2088708888 >> Inspection requested via mobile web by Wes
BLD18-02276 BLD-Foundation7/10/20187/11/20187/11/2018 11:36:52 AMAPASS
Crew is looking to pour at noon. If you can do inspection around 10am that would be great. Thanks! Phone #: ###-#### Inspection requested via web by Gary Gettman
BLD18-01674 BLD-Footing7/10/20187/11/20187/11/2018 7:43:15 AMAPASS
Phone #: ###-####
BLD18-01530 BLD-Energy code compliance7/10/20187/11/20187/11/2018 7:42:56 AMAPASS
Bobby Phone #: ###-####