Inspections for the day of: Friday, February 12, 2010.
Number of inspections: 3
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorSteven Webb
Title 
Phone #794-9491
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
ESC09-00812 Site Preparation2/10/20102/12/20102/12/2010 3:15:53 PMPPART
Walk site with C. Smith: Reviewed site plan with Walt from McAlvain, not ready to approve the start of de-watering, pipe is connected to the pumps but trench construction is just underway. Reviewed pond #2 and 3, should be adequate volume to handle discharge. Inspector #460 will follow up on Tuesday, Feb. 16th. Reminded Walt that trench needs to be lined not bare soil.
ESC39-00001 Site Preparation2/12/20102/12/20102/12/2010 7:47:36 AM CANC
Sample inspection
ESC10-00039 Site Preparation2/12/20102/12/20102/12/2010 7:47:15 AM CANC
Already performed yesterday by Inspector 408