Inspections for the day of: Tuesday, November 20, 2018.
Number of inspections: 24
Percentage of inspections complete: 92 %
Percentage of inspections not complete: 8 %
Contact Information
InspectorDave Hannah
TitleBLD-COM/RES INSPECTOR
Phone #794-1967
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
MIS18-00435 BLD-Conference11/16/201811/16/2018 P 
possible work being done without permits
BLD06-02316 BLD-Footing11/16/201811/19/2018 A 
per Lee has nothing to do with plan mod in review // Lee Phone #: ###-####
BLD17-04515 BLD-Aging Inspection11/20/201811/20/201811/28/2018 12:39:54 PM PEND
BLD18-00604 BLD-Aging Inspection11/20/201811/20/201811/28/2018 12:39:20 PM PEND
MIS18-00090 MIS-Aging Inspection11/20/201811/20/201811/28/2018 12:38:42 PM PEND
BLD17-02757 BLD-Framing/Rough-in11/15/201811/20/201811/28/2018 12:35:30 PMPCANC
Stephen Proctor - Summit Wall: Shaft wall assemblies Level 2; Interior framing on L4; drywall hanging on L3. Phone #: ###-#### Inspection requested via web by Jamal Nelson
BLD18-02901 BLD-Framing/Rough-in11/19/201811/20/201811/20/2018 3:31:58 PMPPASS
Dusty-please call when on way Phone #: ###-####
BLD18-03753 BLD-Framing/Rough-in11/20/201811/20/201811/20/2018 3:31:32 PMPPASS
call 20 min before to meet for access // Zach Smith Phone #: ###-####
BLD16-03998 BLD-Foundation11/20/201811/20/201811/20/2018 2:50:32 PMPPASS
Phone #: 2089656103 >> Inspection requested via mobile web by Alvaro
BLD17-04465 BLD-Framing/Rough-in11/20/201811/20/201811/20/2018 2:12:53 PMPPASS
Framing inspection on Units #101, #201, #111, #113, #115, #117, ; #119 Phone #: ###-#### Inspection requested via web by Hunter Gomez
BLD17-04465 BLD-Energy code compliance11/20/201811/20/201811/20/2018 2:12:38 PMPPASS
Insulation inspection in Units #203, #105, #107, #109 Phone #: ###-#### Inspection requested via web by Hunter Gomez
BLD17-04464 BLD-Wall Bracing11/20/201811/20/201811/20/2018 2:12:19 PMPPART
Inspection of Hold down anchors (HDU4) prior to being covered by framing Phone #: ###-#### Inspection requested via web by Hunter Gomez first floor ok
BLD18-02784 BLD-Framing/Rough-in11/19/201811/20/201811/20/2018 1:37:58 PMPPASS
Chris Phone #: ###-####
BLD17-04285 BLD-Foundation11/19/201811/20/201811/20/2018 1:08:29 PMAPASS
rebar // Justin Phone #: ###-#### meet with al and walked project
BLD17-04285 Extend Permit 90/180 days11/20/201811/20/201811/20/2018 1:07:52 PMPCANC
rebar // Justin Phone #: ###-####
BLD18-03987 BLD-Conference11/19/201811/20/201811/20/2018 11:51:45 AMAPART
Working/occupying with out CO and permit. occ will pick up permit and schedule final inspection
BLD18-03241 BLD-Framing/Rough-in11/19/201811/20/201811/20/2018 11:18:06 AMAPART
Adam Phone #: ###-#### ok to insulate c/n on site needs to strapesbeams topost in living rm
BLD18-01863 BLD-Final11/19/201811/20/201811/20/2018 10:38:21 AMANR
G Phone #: ###-#### needs smoke co2 detectors
BLD18-02192 BLD-Footing11/19/201811/20/201811/20/2018 10:37:53 AMAPASS
Matt Phone #: ###-####
BLD16-01193 BLD-Other11/16/201811/20/201811/20/2018 10:37:40 AMACANC
fire caulking-Ryan Phone #: ###-####650
BLD18-01933 BLD-Final11/19/201811/20/201811/20/2018 9:36:02 AMAPEND
Clinton Phone #: ###-#### ok for temp occ needs to add handrail on aprt and returns on handrails on front steps and ramp
BLD18-01031 BLD-Ceiling Grid Inspection11/19/201811/20/201811/20/2018 9:14:08 AMAPASS
Stan Phone #: ###-####
BLD18-02256 BLD-Wall Bracing11/19/201811/20/201811/20/2018 8:55:46 AMAPASS
Rudy Phone #: ###-####
BLD18-04023 BLD-Foundation11/19/201811/20/201811/20/2018 8:26:13 AMAPASS
Eric Williams Phone #: ###-####