Inspections for the day of: Tuesday, May 19, 2020.
Number of inspections: 11
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorDave Hannah
TitleBLD-COM/RES INSPECTOR
Phone #794-1967
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
BLD20-01463 BLD-Footing5/19/20205/19/20205/21/2020 1:20:32 PMPDONE
An early PM inspection would be great for this inspection. Alex will be doing the installation and his cell number is ###-####. Thanks. Phone #: ###-#### Inspection requested via web by rich prasch
BLD19-04974 BLD-Energy code compliance5/19/20205/19/20205/20/2020 10:07:36 AMPDONE
screened // James Phone #: ###-####
BLD19-03665 BLD-Final5/19/20205/19/20205/19/2020 5:37:17 PMPPASS
Steve Phone #: ###-####
BLD19-03665 DOC - Permit Finaled5/19/20205/19/20205/19/2020 5:37:07 PMPPASS
BLD20-00760 BLD-Framing/Rough-in5/19/20205/19/20205/19/2020 5:36:46 PMPPASS
Phone #: ###-#### Inspection requested via web by Tiffany Cushing
BLD19-03665 DOC - Permit Finaled5/19/20205/19/20205/19/2020 2:37:48 PMPPASS
BLD19-04543 BLD-Framing/Rough-in5/15/20205/19/20205/19/2020 12:58:23 PMPPART
call access- Ashley *screened* Phone #: ###-#### roof truss ok replacment wall framing and headers ok still needs all rought ins done
BLD20-00061 BLD-Concrete5/18/20205/19/20205/19/2020 11:51:49 AMAPASS
basement walls-Tony *screened* Phone #: ###-####
BLD18-00357 BLD-Conference5/15/20205/19/20205/19/2020 11:51:36 AMADONE
Status any change? almost finished
BLD19-00472 BLD-Conference5/15/20205/19/20205/19/2020 9:24:47 AMADONE
Status? ext of project is done
BLD18-01831 BLD-Wall cover5/18/20205/19/20205/19/2020 9:24:47 AMAPASS
Third floor Framing, Front Street. Recap and Review EJ for plumbing assemblies. Possibly review shafts at other areas if complete. Call Adam when heading to site. Thanks. AKJ. Phone #: ###-#### Inspection requested via web by Adam Johnson Phone #: ###-#### Inspection requested via web by Adam Johnson