BLD18-04143
| BLD-Final | 5/17/2019 | 5/21/2019 | 5/28/2019 9:49:06 AM | A | PASS |
|
|
Dave Phone #: ###-####
|
BLD18-03990
| BLD-Footing | 5/20/2019 | 5/21/2019 | 5/22/2019 7:03:30 AM | A | PASS |
|
|
spread footer // Brian Phone #: ###-####
|
BLD18-02566
| BLD-Foundation | 5/21/2019 | 5/21/2019 | 5/22/2019 6:59:19 AM | P | PASS |
|
|
Ed-rebar Phone #: ###-####
|
BLD18-02566
| BLD-Concrete | 5/21/2019 | 5/21/2019 | 5/22/2019 6:59:05 AM | P | PASS |
|
|
Ed-inspection for the pan deck Phone #: ###-####
|
BLD19-00355
| BLD-Conference | 5/21/2019 | 5/21/2019 | 5/21/2019 2:12:30 PM | P | DONE |
|
|
Manny Phone #: ###-#### needs engineer to ok change to ftg size
|
BLD19-00281
| BLD-Final | 5/20/2019 | 5/21/2019 | 5/21/2019 1:12:33 PM | P | PART |
|
|
As early as possible Phone #: 2083188954 >> Inspection requested via mobile web by Jim Douglas ok for tco needs elec to go perm and finish ground floor rest rooms
|
BLD18-02205
| BLD-Foundation | 5/20/2019 | 5/21/2019 | 5/21/2019 8:57:29 AM | A | PASS |
|
|
stem wall// ###-#### Gordon Peterson
|