Inspections for the day of: Tuesday, January 29, 2019.
Number of inspections: 11
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorTroy Cobbley
TitleFIRE INSPECTOR
Phone #794-9483
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
FIR18-00482 INSP-Final Inspection1/28/20191/29/20191/29/2019 3:07:35 PMPFAIL
Need as-builts/plan mods approved as previously requested. I did a walk through to verify the changes have been implemented. No other testing performed.

Please call 30 min prior so that I can meet onsite Phone #: ###-#### Inspection requested via web by Kyle Burgess
BLD18-01064 FIRE-Final Inspection1/29/20191/29/20191/29/2019 2:30:26 PMPPASS
Life safety passed.

Dave Phone #: ###-####
FIR18-00886 INSP-Sprinkler Rough-in1/29/20191/29/20191/29/2019 1:51:30 PMPPASS
See the city approved plans for pendant heads marked "ok" where piping can be covered. I noted several pendants that are overspaced and will need adjusted. I defered the existing pendants fed from the dry system being removed or left installed to plan review.
FIR19-00034 INSP-Final Inspection1/28/20191/29/20191/29/2019 11:15:35 AMAPASS
Permit finaled. Inspection/scope of work was for a micro switch to shut down the power under the hood.

Nate Brain - Technician Phone #: ###-#### Inspection requested via web by Eric Stanley
BLD18-03801 FIRE-Final Inspection1/28/20191/29/20191/29/2019 11:12:42 AMPPASS
Life safety passed

Larren Phone #: ###-####
FIR18-00790 INSP-Final Inspection1/28/20191/29/20191/29/2019 10:32:46 AMACANC
The project related permit for the means of communication was not scheduled/inspected/passed. No inspection performed.

Phone #: ###-#### Inspection requested via web by Kenny Leslie
FIR18-00956 INSP-Final Inspection1/28/20191/29/20191/29/2019 10:26:54 AMACANC
The project related permit for the means of communication was not scheduled/inspected/passed. No inspection performed.

Phone #: ###-#### Inspection requested via web by Ken Webster
BLD17-04133 FIRE-Final Inspection1/28/20191/29/20191/29/2019 10:25:33 AMACANC
Need the project related FIR permits scheduled and finaled prior to a life safety inspection.

Phone #: ###-#### Inspection requested via web by JT Turner
BLD18-00230 FIRE-Final Inspection1/28/20191/29/20191/29/2019 10:25:12 AMACANC
Need the project related FIR permits scheduled and finaled prior to a life safety inspection.

Phone #: ###-#### Inspection requested via web by JT Turner
FIR18-00886 INSP-Sprinkler Rough-in1/28/20191/29/20191/29/2019 9:04:03 AMACANC
Contact Tanner Loomis ###-#### 30 min prior to RTC Insp start please

Thank YOU Phone #: ###-#### >> Inspection requested via web by Teri Cruickshank Inspection cancelled from web by: Teri Cruickshank
FIR18-00886 INSP-Sprinkler Rough-in1/28/20191/29/20191/28/2019 11:06:03 AMACANC
Contact Tanner Loomis ###-#### 30 min prior to RT Insp start please.

Thank YOU Phone #: ###-#### >> Inspection requested via web by Teri Cruickshank Inspection cancelled from web by: Teri Cruickshank