FIR19-00221
| INSP-Sprinkler Rough-in | 1/8/2020 | 1/9/2020 | 1/9/2020 1:44:19 PM | P | PASS |
|
|
The second floor corridor rough-in passed and piping can be covered. The sprinkler work is complete/finaled in the third floor resident rooms.
Tom Phone #: ###-####
|
NAF20-00002
| INSP-Final | 1/9/2020 | 1/9/2020 | 1/9/2020 1:06:26 PM | P | DONE |
|
|
Permit finaled.
Call prior to going Phone #: 2085911821 >> Inspection requested via mobile web by Matt Barnard
|
NAF20-00002
| INSP-Sprinkler Rough-in | 1/9/2020 | 1/9/2020 | 1/9/2020 1:02:24 PM | P | PASS |
|
|
Rough-in passed.
|
FIR19-00863
| INSP-Final Inspection | 1/9/2020 | 1/9/2020 | 1/9/2020 12:41:55 PM | P | FAIL |
|
|
Suppression system functioned. Will be ok to final when as-builts have been provided showing the corrected nozzles.
Phone #: ###-#### Inspection requested via web by Don Kartchner
|
FIR19-00799
| INSP-Sprinkler Rough-in | 1/8/2020 | 1/9/2020 | 1/9/2020 10:58:22 AM | A | PASS |
|
|
Tenting re-inspection passed. Piping can be covered. , call James when heading out. Phone #: ###-#### Inspection requested via web by Anthony Minichiello
|
FIR19-00832
| INSP-Sprinkler Rough-in/Hydro | 1/8/2020 | 1/9/2020 | 1/9/2020 10:42:18 AM | A | PASS |
|
|
Overhead hydro witnessed with no pressure loss.
Gabe Garduno is the contact for his O Hydro inspection. Thank you for your help. Phone #: ###-#### Inspection requested via web by Stan Beus
|
FIR19-00661
| INSP-Sprinkler Rough-in/Hydro | 1/8/2020 | 1/9/2020 | 1/9/2020 10:01:46 AM | A | PASS |
|
|
Overhead Hydro test witnessed with no pressure loss.
, Barry will attend. Phone #: ###-#### Inspection requested via web by Connie Danes
|
FIR19-00718
| INSP-Final Inspection | 1/9/2020 | 1/9/2020 | 1/9/2020 9:29:03 AM | P | CANC |
|
|
Call James when heading out, thanks! Phone #: ###-#### >> Inspection requested via web by Anthony Minichiello Inspection cancelled from web by: Anthony Minichiello
|
FIR19-00774
| INSP-Sprinkler Rough-in | 1/8/2020 | 1/9/2020 | 1/9/2020 8:48:39 AM | A | PASS |
|
|
Underground supply piping is ok for cover. KYLE Phone #: ###-####
|
FIR19-00776
| INSP-Sprinkler Rough-in | 1/8/2020 | 1/9/2020 | 1/9/2020 8:48:04 AM | A | PASS |
|
|
Underground supply piping is ok for cover.
KYLE Phone #: ###-####
|
FIR19-00863
| INSP-Final Inspection | 1/8/2020 | 1/9/2020 | 1/9/2020 8:30:11 AM | A | CANC |
|
|
Phone #: ###-#### >> Inspection requested via web by Don Kartchner Inspection cancelled from web by: Don Kartchner
|
BLD17-01549
| FIRE-Final Inspection | 1/8/2020 | 1/9/2020 | 1/9/2020 7:43:28 AM | A | PASS |
|
|
Life safety passed. Phone #: ###-#### Inspection requested via web by Ron Goff
|
BLD17-01549
| FIRE-Sprinkler Rough-in | 1/8/2020 | 1/9/2020 | 1/9/2020 12:00:00 AM | A | CANC |
|
|
Permit BLD19-01885 finaled for FED EX. No inspection required. **JHB** Phone #: ###-#### >> Inspection requested via web by Ron Goff
|
BLD17-01549
| FIRE-Alarm Testing | 1/8/2020 | 1/9/2020 | 1/9/2020 12:00:00 AM | A | CANC |
|
|
Permit BLD19-01885 finaled for FED EX. No inspection required. **JHB** Phone #: ###-#### >> Inspection requested via web by Ron Goff
|
FIR19-00832
| INSP-Sprinkler Rough-in/Hydro | 1/8/2020 | 1/9/2020 | 1/8/2020 4:42:56 PM | A | CANC |
|
|
Gabe Garduno is the contact for this O Hydro Inspection. Thank you for your help. Phone #: ###-#### >> Inspection requested via web by Stan Beus Inspection cancelled from web by: Stan Beus
|