BLD19-02928
| FIRE-Final Inspection | 10/10/2019 | 10/10/2019 | 10/10/2019 4:29:11 PM | P | PASS |
|
|
Life safety passed. Repair or remove the non-functional exit signs prior to the building inspection. Adam Phone #: ###-####
|
FIR17-00626
| INSP-Final Inspection | 10/9/2019 | 10/10/2019 | 10/10/2019 4:28:10 PM | A | FAIL |
|
|
Placement and function tested. for phase 4 but tech could not provide verification for the candella settings for the strobes in the scope of work. Brian Phone #: ###-####
|
BLD19-00555
| FIRE-Final Inspection | 10/10/2019 | 10/10/2019 | 10/10/2019 2:15:48 PM | A | PASS |
|
|
Life safety passed
Troy, call me. You will need code to get in. Thanks, Todd Phone #: ###-#### Inspection requested via web by Todd Kurns
|
FIR19-00616
| INSP-Final Inspection | 10/10/2019 | 10/10/2019 | 10/10/2019 2:09:50 PM | P | PASS |
|
|
Permit finaled. John Phone #: ###-####
|
FIR18-00503
| INSP-Alarm Testing | 10/9/2019 | 10/10/2019 | 10/10/2019 2:08:35 PM | P | DONE |
|
|
Tested the remaining smoke detectors and elevator recall. Per Lee the volume of the horns has been verified by a third party and is ok. Items need prior to a final sign off are the sync issue with the horns and the previously noted changes need to be applied. Plan mods are needed showing all of the changes.
Contact is Dirk. Phone #: ###-#### Inspection requested via web by Morgan Ahten
|
BLD18-03122
| FIRE-Final Inspection | 10/10/2019 | 10/10/2019 | 10/10/2019 1:25:14 PM | P | PART |
|
|
Life safety passed for apartments 107,108, 207, 208, 307 and 308.- Pat Phone #: ###-####
|
FIR19-00204
| INSP-Final Inspection | 10/10/2019 | 10/10/2019 | 10/10/2019 11:51:08 AM | P | PASS |
|
|
Permit finaled
10:00 A.M. Final Phone #: ###-#### Inspection requested via web by Fire Scheduler
|
BLD19-03932
| FIRE-Final Inspection | 10/9/2019 | 10/10/2019 | 10/10/2019 10:54:20 AM | A | FAIL |
|
|
Remove the thumbturn deadbolt and provide sticker at the main exit, provide a fire extinguisher as discussed.
Call 10 minutes ahead // Rebecca Phone #: ###-####
|
FIR19-00374
| INSP-Final Inspection | 10/9/2019 | 10/10/2019 | 10/10/2019 10:24:04 AM | A | PART |
|
|
Fire sprinkler work complete in apartments 107, 108, 207, 208, 307 and 308.
Gabe Garduno is the contact. This final is for the first 12 units. Thank you for your hard work! Phone #: ###-#### Inspection requested via web by Stan Beus
|
FIR19-00531
| INSP-Supply line flush | 10/9/2019 | 10/10/2019 | 10/10/2019 9:30:13 AM | A | PASS |
|
|
The underground supply line flush was witnessed. . Phone #: ###-#### Inspection requested via web by Matt Barnard
|
FIR19-00733
| INSP-Final Inspection | 10/9/2019 | 10/10/2019 | 10/10/2019 8:40:59 AM | A | PASS |
|
|
Hood suppression system functioned and was verified at the facp. Per the contractor suppression is not required under the hood with the ovens.
Retest for the hood fire system with fixed electrical and fire alarm. Phone #: ###-#### Inspection requested via web by Don Kartchner
|