Inspections for the day of: Tuesday, October 15, 2019.
Number of inspections: 14
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorTroy Cobbley
TitleFIRE INSPECTOR
Phone #794-9483
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
FIR19-00374 INSP-Sprinkler Rough-in10/15/201910/15/201910/15/2019 2:40:42 PMPPART
The sprinkler work is complete in apartments 105, 106, 205, 206, 305 and 306.
BLD18-03122 FIRE-Final Inspection10/14/201910/15/201910/15/2019 1:36:49 PMAPART
Life safety passed for apartments 105, 106, 205, 206, 305 and 306.

matt Phone #: ###-####
BLD18-03486 FIRE-Final Inspection10/14/201910/15/201910/15/2019 1:29:51 PMAPASS
Life safety passed. Phone #: ###-####
NAF18-00086 INSP-Supply line flush10/15/201910/15/201910/15/2019 11:07:07 AMPFAIL
Called contact and left message. Called office and spoke to person to pass on message I was on the way. Arrived and job site with the fire alarm contractor but he was unable to operate flow switch. I also noted missing sprinkler canopy on second floor. I did not continue to third floor tamper switches have not been installed on valves. Will need to check plan mods for clarification. Contact Ken Orahood ###-#### 30 min prior to Final Insp start please.

Thank YOU Phone #: ###-#### Inspection requested via web by Teri Cruickshank
NAF19-00048 INSP-Final10/14/201910/15/201910/15/2019 11:04:23 AMAFAIL
The fire sprinkler contractor was not present to provide testing of the flow switch. Need follow up on tamper switch requirement. Need record of completion when project is finaled. All other devices tested. Call prior to going Phone #: 2088991516 >> Inspection requested via mobile web by John Lopez
BLD19-01233 FIRE-Final Inspection10/11/201910/15/201910/15/2019 10:50:01 AMAPART
A temp for life safety is being given until the as-builts/plan mods are approved.

Thank you. Phone #: ###-#### Inspection requested via web by Jackie Phelps
FIR19-00585 INSP-Final Inspection10/14/201910/15/201910/15/2019 10:48:41 AMAPART
A temporary for fire alarm is being given. Provide as-builts/plan mods showing the strobe candella changes in the Cafeteria and all of the exisiting initiating devices in the scope of work. When plan review approvs the changes permit can be finaled.


Phone #: ###-#### Inspection requested via web by Kristin Dolan
BLD19-01233 FIRE-Alarm Testing10/11/201910/15/201910/15/2019 10:26:38 AMADONE
See the project related fire alarm permit for specifics for the fire alarm testing.
NAF18-00086 INSP-Final10/14/201910/15/201910/15/2019 6:53:30 AMPCANC
Contact ken Orahood ###-#### 30 Min Prior to Final Insp Start please.

Thank YOU Phone #: ###-#### >> Inspection requested via web by Teri Cruickshank Inspection cancelled from web by: Teri Cruickshank
FIR17-00626 INSP-Final Inspection10/14/201910/15/201910/15/2019 6:52:25 AMAPART
Phase 4 fire alarm complete. See the city approved plans for the area clouded in red that was inspected for phase 4.
Brian Phone #: ###-####
FIR19-00353 INSP-Sprinkler Rough-in10/14/201910/15/201910/15/2019 12:00:00 AMPPART
**2nd, 3rd floors, and stairwells OK to cover. Sidewalls changed to Viking EC's in guest rooms over 18'-0"*MAS***
Nick is the contact thank you Phone #: ###-#### >> Inspection requested via web by jeremiah robison
FIR18-00867 INSP-Final Inspection10/14/201910/15/201910/14/2019 4:00:38 PMPCANC
Phone #: ###-#### >> Inspection requested via web by Sam Ball Inspection cancelled from web by: Sam Ball
FIR18-00778 INSP-Final Inspection10/14/201910/15/201910/14/2019 4:00:21 PMPCANC
Phone #: ###-#### >> Inspection requested via web by Sam Ball Inspection cancelled from web by: Sam Ball
NAF18-00086 INSP-Final10/14/201910/15/201910/14/2019 2:19:30 PMPCANC
Contact Andrew Larson ###-#### 30 min prior to Final Insp Start please.

Thank YOU,
Phone #: ###-#### >> Inspection requested via web by Teri Cruickshank Inspection cancelled from web by: Teri Cruickshank