Inspections for the day of: Wednesday, October 2, 2019.
Number of inspections: 12
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorTroy Cobbley
TitleFIRE INSPECTOR
Phone #794-9483
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
BLD18-02473 FIRE-Final Inspection10/2/201910/2/201910/3/2019 6:29:23 AMPFAIL
Provide city approved package/drawings. I noted thumbturn deadbolt on main exit and expired fire extinguishers.

SHERRY Phone #: ###-####
FIR19-00678 INSP-Sprinkler Rough-in/Hydro10/2/201910/2/201910/2/2019 1:57:03 PMPPASS
Underground rough/hydro at Building 10 witnessed with no pressure loss. Piping can be covered. , please call james before heading out. Phone #: ###-#### Inspection requested via web by Anthony Minichiello
BLD17-03056 FIRE-Final Inspection10/2/201910/2/201910/2/2019 1:48:07 PMPFAIL
Provide city approved package/drawings. I noted thumbturn deadbolt on main exit and expired fire extinguishers.

SHERRY Phone #: ###-####
FIR18-00503 INSP-Alarm Testing10/1/201910/2/201910/2/2019 1:05:34 PMPDONE
Today we finished the building walk through for the notification appliances. See the city approved plans for locations of deficiencies. Approx. 30 items. The fire alarm panel currently has dial out issues and does not appear to be reporting signals. Plans need to be resubmitted showing the candella changes and that many of the smoke detectors have not been installed. No smoke detectors were tested due to the communication troubles on the fire alarm panel.

Contact is Dirk. Phone #: ###-#### Inspection requested via web by Morgan Ahten
BLD18-03121 FIRE-Final Inspection10/2/201910/2/201910/2/2019 1:02:42 PMPFAIL
Apartment 201 needs the ceiling patched in several locations and the smoke alarm re-mounted. Apartment 301 sprinkler pendant is missing canopy.

Matt Phone #: ###-####
FIR19-00718 INSP-Sprinkler Rough-in/Hydro9/30/201910/2/201910/2/2019 1:01:29 PMAPART
Rough-in passed but as-builts need to be submitted showing changes. No piping to be covered until as-builts are provided and a tenting inspection has been passed. The supply piping to the riser has not been provided yet. Please call James before heading out, thanks! Phone #: ###-#### Inspection requested via web by Anthony Minichiello
FIR19-00372 INSP-Final Inspection10/2/201910/2/201910/2/2019 12:58:46 PMPPASS
Permit finaled. Per contractor the irrigation system is separate and does not require the automatic shut off valve.

Please call James before heading out! Phone #: ###-#### Inspection requested via web by Anthony Minichiello
FIR19-00374 INSP-Final Inspection10/1/201910/2/201910/2/2019 11:16:54 AMACANC
Wrong permit number/building scheduled. Gabe Garduno is the contact for this final inspection. He is requesting an inspection for section 03 and 04. Thank you for your help. Have a nice day. Phone #: ###-#### Inspection requested via web by Stan Beus
FIR18-00699 INSP-Final Inspection10/1/201910/2/201910/2/2019 10:18:54 AMAPASS
Permit finaled
FIR19-00599 INSP-Sprinkler Rough-in10/1/201910/2/201910/2/2019 10:07:01 AMAPASS
See the city approved plans for area where branchline and main rough-in took place. I noted that upright sprinkler heads are overspace at two restroom locations if the sheet rock goes to the deck. Kenny Caldwell is the contact for this rough to cover inspection. Thank you for your help. Have a nice day. Phone #: ###-#### Inspection requested via web by Stan Beus
BLD19-03627 FIRE-Final Inspection10/1/201910/2/201910/2/2019 10:05:39 AMAPASS
Life safety passed. Tim Phone #: ###-####
FIR19-00544 INSP-Sprinkler Rough-in10/1/201910/2/201910/2/2019 8:26:43 AMAPASS
See the city approved plans for piping above hardlids that is ok for cover.

Contact Noemi Carerro ###-#### 30 min prior to RTC Insp start please, this insp is for the hard lids please.

Thank YOU Phone #: ###-#### Inspection requested via web by Teri Cruickshank