FIR18-00583
| INSP-Sprinkler Rough-in | 11/13/2018 | 11/13/2018 | 11/13/2018 4:08:53 PM | P | FAIL |
|
|
No city approved plans for the areas requested for inspection
Tony Cetani is the contact. Thanks. Phone #: ###-#### Inspection requested via web by Stan Beus
|
FIR18-00708
| INSP-Sprinkler Rough-in | 11/13/2018 | 11/13/2018 | 11/13/2018 4:08:24 PM | P | FAIL |
|
|
No city approved plans for the areas requested for inspection
Tony Cetani is the contact. Thanks. Phone #: ###-#### Inspection requested via web by Stan Beus
|
FIR18-00583
| INSP-Sprinkler Rough-in/Hydro | 11/13/2018 | 11/13/2018 | 11/13/2018 4:07:39 PM | P | FAIL |
|
|
Not ready for hydro since all heads have not been cut in.
Tony Cetani is the contact. Thanks. Phone #: ###-#### Inspection requested via web by Stan Beus
|
FIR18-00708
| INSP-Sprinkler Rough-in/Hydro | 11/13/2018 | 11/13/2018 | 11/13/2018 4:07:08 PM | P | FAIL |
|
|
Not ready for hydro since all heads have not been cut in.
Tony Cetani is the contact. Thanks:) Phone #: ###-#### Inspection requested via web by Stan Beus
|
BLD18-02709
| FIRE-Final Inspection | 11/13/2018 | 11/13/2018 | 11/13/2018 3:43:31 PM | P | CANC |
|
|
This was scheduled for the wrong day. Is rescheduled for tomorrow with the fire alarm inspection.
Inspection requested via web by Brad Cooper
|
BLD18-02545
| FIRE-Final Inspection | 11/13/2018 | 11/13/2018 | 11/13/2018 3:02:21 PM | P | PART |
|
|
A temporary for life safety is ok with Ron until the fire sprinkler and fire alarm modifications have been performed. Standard time length applies.
Devin Phone #: ###-####
|
FIR18-00787
| INSP-Sprinkler Rough-in | 11/7/2018 | 11/13/2018 | 11/13/2018 2:59:25 PM | P | CANC |
|
|
Per the fitter the revised plans have not been approved yet. No inspection was performed.
Phone #: ###-#### Inspection requested via web by Stan Beus
|
FIR18-00298
| INSP-Sprinkler Rough-in | 11/12/2018 | 11/13/2018 | 11/13/2018 2:09:49 PM | P | PART |
|
|
The rough-in for the most part is passed. It appeears additional hangers are needed for the cpvc piping. Also as-builts need to be approved showing all of the additional fittings that have been added including the two 90's at the base of the riser and the 90's added on the cpvc piping grid lines.
Contact Scott Powada ###-#### 30 min prior to RTC Insp start please
Thank YOU Phone #: ###-#### Inspection requested via web by Teri Cruickshank
|
FIR18-00414
| INSP-Final Inspection | 11/9/2018 | 11/13/2018 | 11/13/2018 1:54:58 PM | P | CANC |
|
|
The fire alarm inspection failed. No sprinkler permit items tested.
Phone #: ###-#### Inspection requested via web by Stan Beus
|
BLD18-01850
| FIRE-Final Inspection | 11/9/2018 | 11/13/2018 | 11/13/2018 12:58:06 PM | A | PASS |
|
|
Life safety passed. No sprinkler work
Please give me a call ahead of time ###-#### thanks Mike Teeter Inspection requested via web by Mike Teeter
|
BLD18-01423
| FIRE-Final Inspection | 11/9/2018 | 11/13/2018 | 11/13/2018 12:20:56 PM | A | PASS |
|
|
Life safety passed. The thumbturn deadbolt on the Pick and Go room needs removed prior to a building inspection as per our conversation
please give me a call ahead of time ###-#### thanks Mike Teeter Inspection requested via web by Mike Teeter
|
FIR18-00544
| INSP-Supply line flush | 11/8/2018 | 11/13/2018 | 11/13/2018 11:29:15 AM | P | CANC |
|
|
Phone #: ###-#### Inspection requested via web by Stan Beus
|
FIR18-00544
| INSP-Sprinkler Rough-in/Hydro | 11/8/2018 | 11/13/2018 | 11/13/2018 11:28:59 AM | P | CANC |
|
|
Problem with the hydro pump.
Phone #: ###-#### Inspection requested via web by Stan Beus
|
FIR18-00545
| INSP-Supply line flush | 11/8/2018 | 11/13/2018 | 11/13/2018 11:28:24 AM | P | CANC |
|
|
Phone #: ###-#### Inspection requested via web by Stan Beus
|
FIR18-00545
| INSP-Sprinkler Rough-in/Hydro | 11/8/2018 | 11/13/2018 | 11/13/2018 11:28:09 AM | P | CANC |
|
|
Problem with hydro pump.
Phone #: ###-#### Inspection requested via web by Stan Beus
|
FIR18-00608
| INSP-Supply line flush | 11/8/2018 | 11/13/2018 | 11/13/2018 11:27:40 AM | P | CANC |
|
|
Phone #: ###-#### Inspection requested via web by Stan Beus
|
FIR18-00608
| INSP-Sprinkler Rough-in/Hydro | 11/8/2018 | 11/13/2018 | 11/13/2018 11:27:22 AM | P | CANC |
|
|
Problem with hydro pump
Phone #: ###-#### Inspection requested via web by Stan Beus
|
FIR18-00601
| INSP-Supply line flush | 11/8/2018 | 11/13/2018 | 11/13/2018 11:26:52 AM | P | CANC |
|
|
Phone #: ###-#### Inspection requested via web by Stan Beus
|
FIR18-00601
| INSP-Sprinkler Rough-in/Hydro | 11/8/2018 | 11/13/2018 | 11/13/2018 11:26:38 AM | P | CANC |
|
|
Problem with hydro pump
Phone #: ###-#### Inspection requested via web by Stan Beus
|
FIR18-00813
| INSP-Supply line flush | 11/8/2018 | 11/13/2018 | 11/13/2018 11:26:06 AM | P | CANC |
|
|
Phone #: ###-#### Inspection requested via web by Stan Beus
|
FIR18-00813
| INSP-Sprinkler Rough-in/Hydro | 11/8/2018 | 11/13/2018 | 11/13/2018 11:25:47 AM | P | FAIL |
|
|
Piping was not holding minimum starting pressure
Phone #: ###-#### Inspection requested via web by Stan Beus
|
FIR18-00563
| INSP-Supply line flush | 11/8/2018 | 11/13/2018 | 11/13/2018 11:24:54 AM | P | CANC |
|
|
Problem with hydro pump
Phone #: ###-#### Inspection requested via web by Stan Beus
|
FIR18-00563
| INSP-Sprinkler Rough-in/Hydro | 11/8/2018 | 11/13/2018 | 11/13/2018 11:24:20 AM | P | CANC |
|
|
Problem with hydro pump
Phone #: ###-#### Inspection requested via web by Stan Beus
|
FIR18-00562
| INSP-Sprinkler Rough-in/Hydro | 11/8/2018 | 11/13/2018 | 11/13/2018 11:23:42 AM | P | CANC |
|
|
Problem with hydro pump
Hydro Phone #: ###-#### Inspection requested via web by Stan Beus
|
FIR18-00519
| INSP-Supply line flush | 11/8/2018 | 11/13/2018 | 11/13/2018 11:22:59 AM | P | CANC |
|
|
Problem with hydro pump.
|
FIR18-00519
| INSP-Sprinkler Rough-in/Hydro | 11/8/2018 | 11/13/2018 | 11/13/2018 11:22:03 AM | P | FAIL |
|
|
Underground supply was not at the minimum starting pressure for a hydro test.
Phone #: ###-#### Inspection requested via web by Stan Beus
|
FIR18-00562
| INSP-Supply line flush | 11/8/2018 | 11/13/2018 | 11/13/2018 11:18:54 AM | P | CANC |
|
|
Not ready due to pump problems
Phone #: ###-#### Inspection requested via web by Stan Beus
|
FIR18-00609
| INSP-Sprinkler Rough-in/Hydro | 11/9/2018 | 11/13/2018 | 11/13/2018 10:48:30 AM | A | PART |
|
|
Overhead Rough-In is partially passed. See the city approved plans for corrections needed with some earthquake bracing. Also need ceilings removed to inspect the new sprinkler piping. As-builts will be required prior to a final sign off showing the riser being relocated and some small pipe size changes and new area being sprinklered. The overhead hydro inspection passed with no visible loss on the guage.. Cesar Rodriguez is Foreman Phone #: ###-#### Inspection requested via web by Brett Lawatch
|
FIR18-00590
| INSP-Sprinkler Rough-in | 11/12/2018 | 11/13/2018 | 11/13/2018 10:22:28 AM | A | PASS |
|
|
See the city approved plans for rooms marked "ok" where sprinkler piping can be covered. I noted in a few rooms that the upright sprinkler protection is blocked by duct work and will need to meet the obstruction charts of NFPA 13
|
FIR18-00592
| INSP-Sprinkler Rough-in | 11/9/2018 | 11/13/2018 | 11/13/2018 9:35:20 AM | A | PASS |
|
|
The sprinkler piping above the hardlids in the Restrooms is ok for cover.
|
FIR18-00767
| INSP-Final Inspection | 11/12/2018 | 11/13/2018 | 11/13/2018 9:19:25 AM | A | FAIL |
|
|
No access to the fire alarm panel. Lock is brocken. Will need to be rescheduled.
|