FIR18-00911
| INSP-Sprinkler Rough-in | 12/17/2018 | 12/17/2018 | 12/17/2018 3:06:14 PM | A | PASS |
|
|
Provide missing hanger and missing head at the top of the stairs. Piping is ok for cover.
Call Anthony before heading out, thanks! Phone #: ###-#### Inspection requested via web by Anthony Minichiello
|
BLD18-01064
| FIRE-Final Inspection | 12/14/2018 | 12/17/2018 | 12/17/2018 2:39:51 PM | P | PART |
|
|
Phase 1 life safety passed.
lobby 2nd and 1st and 3rd floor-Dave Phone #: ###-####
|
BLD18-01593
| FIRE-Final Inspection | 12/17/2018 | 12/17/2018 | 12/17/2018 2:38:55 PM | P | PART |
|
|
Life safety for the Link is passed. Dave is going to place fire extinguishers at both ends of the Link. An additional stobe is needed at the Building 36 (LOBBY) end of the link. I spoke to Ron with Boise Fire about this. A separate permit will be needed for this work.
dave Phone #: ###-####
|
FIR18-00455
| INSP-Alarm Testing | 12/17/2018 | 12/17/2018 | 12/17/2018 2:36:45 PM | P | PART |
|
|
Phase 1 fire alarm work is complete.
Phone #: 2088301311 >> Inspection requested via mobile web by Nathan Price
|
FIR18-00455
| INSP-Final Inspection | 12/17/2018 | 12/17/2018 | 12/17/2018 2:34:35 PM | P | PART |
|
|
Phase 1 fire alarm work complete. The smoke detectors for elevator return now send alarm not supervisory signals.
Adam Phone #: ###-####
|
FIR18-00919
| INSP-Final Inspection | 12/17/2018 | 12/17/2018 | 12/17/2018 2:33:13 PM | P | PART |
|
|
Fire alarm work for the Link is complete. Two smoke detectors need to be relocated so that they are centered in the doors at both ends. This will be checked at the next inspection.
phase 1- Adam Phone #: ###-####
|
FIR18-00592
| INSP-Final Inspection | 12/14/2018 | 12/17/2018 | 12/17/2018 12:29:07 PM | P | CANC |
|
|
Contact Ken Orahood ###-#### 30 min prior to Fire Final Insp start please
Thank YOU Phone #: ###-#### >> Inspection requested via web by Teri Cruickshank Inspection cancelled from web by: Teri Cruickshank
|
FIR18-00482
| INSP-Final Inspection | 12/14/2018 | 12/17/2018 | 12/17/2018 11:55:25 AM | P | FAIL |
|
|
Project is not ready for a final yet. During the initial walk through I found over spaced stobes and one area where new costruction, not shown on the plans, has caused spacing issues with the strobes. Contractor is going to provide as-builts with the modified candellas and addtional strobes required for the new construction. Also I noted to small rooms being used as open office areas that will require notificaiton. No other testing was performed.
Please call before arrival so I can plan to meet at site. Phone #: ###-#### Inspection requested via web by Kyle Burgess
|
FIR18-00787
| INSP-Sprinkler Rough-in | 12/13/2018 | 12/17/2018 | 12/17/2018 10:01:09 AM | A | PASS |
|
|
Rough-in passed. Tenting passed. Piping is ok for cover. Supply piping size to the backflow preventor does not match plans and will need addressed prior to a final sign off.
Marcus Smith is the contact for this RTC inspection. Thank you for your help. Phone #: ###-#### Inspection requested via web by Stan Beus
|
BLD18-03804
| FIRE-Final Inspection | 12/16/2018 | 12/17/2018 | 12/17/2018 9:38:49 AM | A | PASS |
|
|
Life safety passed. Permit number on line did not match the one on the plans. It was corrected.
|