Inspections for the day of: Friday, December 20, 2019.
Number of inspections: 5
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorTroy Cobbley
TitleFIRE INSPECTOR
Phone #794-9483
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
FIR19-00318 INSP-Final Inspection12/19/201912/20/201912/20/2019 2:34:01 PMPFAIL
The common area smoke detectors for first and second floors tested ok. The elevator recall failed. All elevator devices will need to be retested when issue is resolved.

Phone #: 2088301311 >> Inspection requested via mobile web by Nathan Price
FIR19-00887 INSP-Sprinkler Rough-in12/20/201912/20/201912/20/2019 12:02:22 PMPPART
Rough-in is ok but piping can not be covered until the insulation at the roof deck has been repaired.

Contact: Nick Curtis
Site is open for inspection all day. Phone #: ###-#### Inspection requested via web by Hunter Fillmore
FIR19-00754 INSP-Sprinkler Rough-in/Hydro12/19/201912/20/201912/20/2019 11:59:37 AMAPASS
The combustible concealed space below the ramp has been filled with insulation.

George Jess is the contact. This is for an overhead Hydro. Thanks for all you do! Phone #: ###-#### Inspection requested via web by Stan Beus
FIR19-00373 INSP-Supply line flush12/19/201912/20/201912/20/2019 11:28:44 AMAPASS
The underground flush was witnessed.

Todd is the contact. Thanks for all you! Phone #: ###-#### Inspection requested via web by Stan Beus
FIR19-00662 INSP-Sprinkler Rough-in/Hydro12/19/201912/20/201912/20/2019 11:28:08 AMAPASS
The underground hydro was witnessed with no pressure loss.

George Jess is the contact. This is for an UG Hydro. Thanks for all you do. Phone #: ###-#### Inspection requested via web by Stan Beus