Inspections for the day of: Tuesday, December 3, 2019.
Number of inspections: 10
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorTroy Cobbley
TitleFIRE INSPECTOR
Phone #794-9483
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
FIR19-00172 INSP-Final Inspection12/2/201912/3/201912/3/2019 3:06:08 PMAFAIL
Permit will be ok to final when the plan mods have been approved.

As early as possible Phone #: 2088301311 >> Inspection requested via mobile web by Nathan Price
FIR19-00353 INSP-Sprinkler Rough-in12/3/201912/3/201912/3/2019 2:18:47 PMPPASS
2nd floor hard lids are ok for cover. thank you Phone #: ###-#### Inspection requested via web by jeremiah robison
BLD18-02176 FIRE-Final Inspection12/3/201912/3/201912/3/2019 1:52:16 PMPFAIL
Inspection was actually for a conference to provide guide lines for the use of the south end/sales are for a Christmas function. It appears the gate for the existing fire hydrant needs installed, building address, Riser and Electrical Room signage, grading permit sign off, fire extinguishers mounted and a fire dept approved temp barrier to the rest of the building. Also needed is a building inspection and approval for the use of the building/area.

Nacho Phone #: ###-####
BLD19-04697 FIRE-Final Inspection12/2/201912/3/201912/3/2019 1:26:07 PMPFAIL
Provide annual inspection tag for fire extinguisher, provide sticker at door and suite number.

Shaun Phone #: ###-####
FIR19-00511 INSP-Sprinkler Rough-in/Hydro12/2/201912/3/201912/3/2019 1:14:38 PMPPASS
Overhead hydro passed. George Jess is the contact. Thanks for all you do! Phone #: ###-#### Inspection requested via web by Stan Beus
FIR19-00290 INSP-Sprinkler Rough-in/Hydro12/3/201912/3/201912/3/2019 1:14:06 PMPPASS
Overhead hydro passed and pendants have been modified in the second open office.

Todd Ketterling is the contact. Thanks for all you do! Phone #: ###-#### Inspection requested via web by Stan Beus
BLD19-03209 FIRE-Final Inspection12/2/201912/3/201912/3/2019 10:22:15 AMAPART
Life safety passed for Phase 1/Building B. Will need the project related fire alarm permit finaled prior to a Phase 1 sign off.

Tom Phone #: ###-####
FIR18-00886 INSP-Final Inspection12/2/201912/3/201912/3/2019 10:07:35 AMAFAIL
Not ready for a final yet. This inspection is for a sprinkler rough-in. See the city approved plans additional heads where piping is ok for cover. I noted on pendant that still needs changed to quick responce and verification that the extended coverage heads can be used in a Storage Room.

Contact Hunter Anderson ###-#### 30 min prior to TCO/Final Insp start please Hunter prefers an early AM inspection if possible

Thank YOU Phone #: ###-#### Inspection requested via web by Teri Cruickshank
FIR18-00957 INSP-Final Inspection12/2/201912/3/201912/3/2019 8:49:28 AMAPASS
Permit finaled. Forward flush witnessed. Phone #: ###-####
BLD19-04343 FIRE-Final Inspection12/2/201912/3/201912/3/2019 8:48:58 AMAPASS
Life safety passed.

Call ahead // Jesse Phone #: ###-####