Inspections for the day of: Monday, December 9, 2019.
Number of inspections: 16
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorTroy Cobbley
TitleFIRE INSPECTOR
Phone #794-9483
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
FIR18-00892 INSP-Sprinkler Rough-in/Hydro12/6/201912/9/201912/9/2019 3:12:01 PMPCANC
Needed flush not rough-in.

Barry is ready for you. Phone #: ###-#### Inspection requested via web by Connie Danes
FIR18-00892 INSP-Supply line flush12/9/201912/9/201912/9/2019 3:11:21 PMPPASS
Underground flush witnessed.

Barry is ready for you. Phone #: ###-#### Inspection requested via web by Connie Danes
FIR19-00661 INSP-Supply line flush12/9/201912/9/201912/9/2019 3:10:55 PMPPASS
Underground flush witnessed.

Barry Phone #: ###-#### Inspection requested via web by Connie Danes
FIR19-00553 INSP-Final Inspection12/9/201912/9/201912/9/2019 1:42:55 PMPPASS
Permit finaled.

Kenny Phone #: ###-####
BLD18-04527 FIRE-Final Inspection12/6/201912/9/201912/9/2019 12:46:37 PMAPASS
Life safety passed.

Jay Phone #: ###-####
FIR19-00807 INSP-Final Inspection12/6/201912/9/201912/9/2019 12:33:52 PMAPASS
Permit finaled. Phone #: 2086157641 >> Inspection requested via mobile web by Richard Johnson
FIR19-00321 INSP-Final Inspection12/9/201912/9/201912/9/2019 11:55:45 AMPCANC
Please all Jess before heading down. Phone #: ###-#### >> Inspection requested via web by Jessia Maxwell Inspection cancelled from web by: Jessia Maxwell
FIR19-00766 INSP-Sprinkler Rough-in12/9/201912/9/201912/9/2019 11:25:39 AMAFAIL
Tenting inspection failed. I sent pictures of the three areas of concern to Ken and explained my concerns. Re-inspection fee applied.

Contact Ken Orahood ###-#### 30 minc prior to Insp start please. We''ve been told that they are ready and the Tenting has been taken care of hopefully for the last time.

Thank YOU Phone #: ###-#### Inspection requested via web by Teri Cruickshank
FIR19-00913 INSP-Final Inspection12/6/201912/9/201912/9/2019 9:40:28 AMAPASS
Permit finaled. Contact is Dan. Phone #: ###-#### Inspection requested via web by Morgan Ahten
BLD19-02117 FIRE-Final Inspection12/9/201912/9/201912/9/2019 9:39:56 AMPPART
A temp for life safety is ok'd by Joe Bruce until the gas islands have been completed/inspected. Previous corrections have been addressed. Nate Phone #: ###-####
BLD19-00294 FIRE-Final Inspection12/9/201912/9/201912/9/2019 9:39:32 AMPPART
A temp for life safety is ok'd by Joe Bruce until the gas islands have been completed/inspected. Previous corrections have been addressed. Nate Phone #: ###-####
BLD19-00294 FIRE-Final Inspection12/6/201912/9/201912/9/2019 9:39:05 AMAPART
A temp for life safety is ok'd by Joe Bruce until the gas islands have been completed/inspected. Previous corrections have been addressed. Nate Phone #: ###-####
FIR19-00334 INSP-Final Inspection12/6/201912/9/201912/9/2019 8:48:43 AMAPASS
Permit finaled.

Contact is Dan. Phone #: ###-#### Inspection requested via web by Morgan Ahten
BLD19-03430 FIRE-Final Inspection12/6/201912/9/201912/9/2019 8:48:05 AMAPASS
Life safety passed. Card signed. Rick Phone #: ###-####
FIR19-00672 INSP-Final Inspection12/6/201912/9/201912/9/2019 12:00:00 AMAPASS
**PASS** Hydro papers and paperwork showing factory painted escutcheons uploaded to tidemark*MAS** Gabe is the contact. Thanks for all you do! Phone #: ###-#### >> Inspection requested via web by Stan Beus
NAF19-00071 INSP-Final12/6/201912/9/201912/9/2019 12:00:00 AMAPASS
***PASS Hydro papers uploaded to tidemark*MAS*** Gabe is the contact. Thanks for all you do! Phone #: ###-#### >> Inspection requested via web by Stan Beus