Inspections for the day of: Friday, February 1, 2019.
Number of inspections: 10
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorTroy Cobbley
TitleFIRE INSPECTOR
Phone #794-9483
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
FIR18-00564 INSP-Sprinkler Rough-in2/1/20192/1/20192/1/2019 2:35:27 PMPCANC
No city approved plans on site, no inspetion. Johnathon Phone #: ###-####
FIR18-00565 INSP-Sprinkler Rough-in2/1/20192/1/20192/1/2019 2:35:04 PMPCANC
No city approved plans on site. No inspection. Johnathon Phone #: ###-####
FIR18-00675 INSP-Sprinkler Rough-in/Hydro1/31/20192/1/20192/1/2019 2:34:35 PMPPASS
See the city approved plans for locations in the south side of building where sprinkler piping can be covered. I also looked at the overhead sprinkler piping in the Kitchen/Cooler area. Another rough-in inspection will be needed for cover when the T-bar and pendants in this area have been installed. Right now it is just the supply piping at the roof deck.

Cesear Phone #: ###-####
FIR18-00675 INSP-Supply line flush1/31/20192/1/20192/1/2019 1:30:10 PMPPASS
Underground flush passed

Cesear Phone #: ###-####
NAF18-00086 INSP-Sprinkler Rough-in2/1/20192/1/20192/1/2019 1:08:02 PMPPART
No city approved plans/small documents on site. No inspection performed but we did talk about cover inspection procedure on the project.
FIR19-00070 INSP-Final Inspection1/31/20192/1/20192/1/2019 10:52:28 AMAPASS
permit finaled

Phone #: ###-#### Inspection requested via web by Sam Ball
NAF18-00086 INSP-Sprinkler Rough-in1/31/20192/1/20192/1/2019 10:34:39 AMACANC
Contact Andrew Larson - ###-#### 30 Min Prior to RTC Insp start please

Thank YOU,
Teri Phone #: ###-#### >> Inspection requested via web by Teri Cruickshank Inspection cancelled from web by: Teri Cruickshank
FIR17-00603 INSP-Sprinkler Rough-in1/31/20192/1/20192/1/2019 9:59:32 AMAPASS
See the city approved plans for location marked "ok" where sprinkler piping is ok for cover.

Todd Ketterling is your contact. Thanks for the hard work! Phone #: ###-#### Inspection requested via web by Stan Beus
FIR17-00626 INSP-Alarm Testing1/30/20192/1/20192/1/2019 9:26:52 AMAFAIL
The signals did go to the airport control as device and room number but the airport did not have an actual description of the location on site for the alarm. Gary is going to add description and reschedule.

Re-inspect after placing ARFF building on airport network - verification testing that new building reports to the Airport operations center. Phone #: ###-#### Inspection requested via web by Shane Lesteberg
FIR16-00810 INSP-Final Inspection1/31/20192/1/20192/1/2019 8:24:50 AMAPASS
permit finaled

Thanks. Call Jeff if there are questions. Phone #: ###-#### Inspection requested via web by Jeff Packham