FIR18-00901
| INSP-Sprinkler Rough-in | 2/11/2019 | 2/11/2019 | 2/11/2019 2:45:43 PM | P | PASS |
|
|
General overhead rough-in passed. Still need earthquake bracing installed and verified.
Mike Phone #: ###-####
|
BLD18-03042
| FIRE-Final Inspection | 2/11/2019 | 2/11/2019 | 2/11/2019 2:04:14 PM | P | FAIL |
|
|
Need project related fire alarm and fire sprinkler permits finaled, need knox key box, need signage on the Riser Room and FACP/Electrical Room, need max occupant load signs, need small documents.
Bob Phone #: ###-####
|
FIR19-00073
| INSP-Final Inspection | 2/8/2019 | 2/11/2019 | 2/11/2019 1:28:30 PM | P | FAIL |
|
|
Plan mods are needed showing the DMP dialer that has been added and the notification devices that have been deleted. Need knox key box.
Need to test the dry system interconnects.Contact is Dirk. Phone #: ###-#### Inspection requested via web by Morgan Ahten
|
FIR18-00915
| INSP-Final Inspection | 2/7/2019 | 2/11/2019 | 2/11/2019 1:27:51 PM | P | FAIL |
|
|
Need to have access to verify the insulation has been installed since the ceiling were put in.
Contact Leroy Anderson ###-#### 30 min prior to Fire Final start please.
Thank YOU Phone #: ###-#### Inspection requested via web by Scott Carter II
|