Inspections for the day of: Friday, February 16, 2018.
Number of inspections: 9
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorTroy Cobbley
TitleFIRE INSPECTOR
Phone #794-9483
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
BLD14-02837 FIRE-Final Inspection2/16/20182/16/20182/16/2018 12:21:39 PMPPASS
Life safety passed for project scope of work.


Lee Phone #: ###-####
BLD17-04025 FIRE-Final Inspection2/15/20182/16/20182/16/2018 12:10:09 PMPCANC
Chad Phone #: ###-####
FIR17-00576 INSP-Sprinkler Rough-in2/15/20182/16/20182/16/2018 10:51:21 AMAPASS
Ceiling tile is ok to install as marked on plans except a tile/access is needed at the fire proofing patch locations so work can be verified at the next inspection.
BLD17-04297 FIRE-Conference2/16/20182/16/20182/16/2018 10:24:14 AMPDONE
Conference was to discuss whether fire sprinkler protection would be required in the new canopy. Per the fire review comments none are required with conditions

Cody Phone #: ###-####
BLD17-02915 FIRE-Final Inspection2/16/20182/16/20182/16/2018 10:23:15 AMPPART
A temporary for life safety is being given until the exit discharge light is installed at the main exit.


Bruce Phone #: ###-####
FIR17-00670 INSP-Sprinkler Rough-in/Hydro2/15/20182/16/20182/16/2018 9:00:32 AMAPASS
Overhead hydro test passed
BLD17-04532 FIRE-Final Inspection2/15/20182/16/20182/16/2018 7:43:37 AMAPASS
life safety passed


Tim-please call 30 minutes prior to meet for access Phone #: ###-####
FIR16-00821 INSP-Final Inspection2/15/20182/16/20182/16/2018 12:00:00 AMACANC
MIKE IS OUR FOREMAN THIS IS IN CONJUNCTION WITH THE ALARM CONTRACTOR Phone #: ###-#### >> Inspection requested via web by Brad Bettencourt
BLD17-00396 FIRE-Final Inspection2/15/20182/16/20182/15/2018 3:04:07 PMAPASS
Life safety passed. Contractor is installing blanks on the dead bolts. Address is installed and a smaller refrigerator has been installed.

Josh Phone #: ###-####