BLD19-03898
| FIRE-Final Inspection | 2/21/2020 | 2/21/2020 | 2/21/2020 2:14:39 PM | P | FAIL |
|
|
Need the project related fire alarm permit finaled. Need the two exit signs modified as discussed. Need suite number posted. All other items appear ok. Phone #: ###-#### Inspection requested via web by Nate Carriveau
|
FIR19-00890
| INSP-Final Inspection | 2/21/2020 | 2/21/2020 | 2/21/2020 2:13:00 PM | P | PASS |
|
|
Permit finaled.
Richard Phone #: ###-####
|
FIR19-00883
| INSP-Final Inspection | 2/21/2020 | 2/21/2020 | 2/21/2020 2:12:31 PM | P | FAIL |
|
|
No testing performed. During walk through I fould many of the strobes overspaced and areas missing notificaiton. Contractor needs to perform a walk through and modify coverage to meet min. code. Plans need to be resubmitted showing the changes for approval before the next scheduled inspection.
Contact is Dirk. Phone #: ###-#### Inspection requested via web by Morgan Ahten
|
FIR19-00353
| INSP-Sprinkler Rough-in | 2/20/2020 | 2/21/2020 | 2/21/2020 10:48:06 AM | A | PASS |
|
|
The revised location for the earth quake bracing at the Risers is ok. Piping above the hardlids in the 1st floor entry lobby is ok for cover.
Thank you Phone #: ###-#### Inspection requested via web by jeremiah robison
|
BLD19-02218
| FIRE-Final Inspection | 2/20/2020 | 2/21/2020 | 2/21/2020 10:05:20 AM | A | PASS |
|
|
Life safety passed.
Mike Phone #: ###-####
|
FIR18-00188
| INSP-Final Inspection | 2/14/2020 | 2/21/2020 | 2/21/2020 9:03:42 AM | A | PASS |
|
|
Permit finalede.
Peter will be onsite at 8:00 please Phone #: ###-#### Inspection requested via web by Fire Scheduler
|
FIR20-00052
| INSP-Sprinkler Rough-in | 2/20/2020 | 2/21/2020 | 2/21/2020 9:02:01 AM | A | PASS |
|
|
Rough-in passed. Piping can be covered. Plan review is ok with two pendants from a 1" outlet.Payton Nelson Phone #: ###-####
|
BLD19-04625
| FIRE-Final Inspection | 2/20/2020 | 2/21/2020 | 2/21/2020 7:59:24 AM | A | PART |
|
|
The life safety in the Gym area is complete. Fire alarm and fire sprinkler as well.
John Phone #: ###-####
|
FIR20-00019
| INSP-Final Inspection | 2/19/2020 | 2/21/2020 | 2/21/2020 7:56:34 AM | A | PART |
|
|
The fire alarm work in the Gym area is complete.
Contact is Dan. Requesting 7am inspection time. Troy has been contacted already concerning this. Phone #: ###-#### Inspection requested via web by Morgan Ahten
|
FIR19-00958
| INSP-Final Inspection | 2/20/2020 | 2/21/2020 | 2/21/2020 7:56:00 AM | A | PART |
|
|
The sprinkler work in the Gym area is complete.
Phone #: ###-#### Inspection requested via web by Sam Ball
|