Inspections for the day of: Wednesday, February 24, 2016.
Number of inspections: 13
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorTroy Cobbley
TitleFIRE INSPECTOR
Phone #794-9483
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
BLD15-02560 FIRE-Final Inspection2/24/20162/24/20162/25/2016 10:18:55 AMPPASS
life safety passed
FIR16-00104 INSP-Sprinkler Rough-in/Hydro2/23/20162/24/20162/24/2016 3:04:42 PMPFAIL
Todays inspection was for the east building. Almost all of the underground supply piping has been installed/covered by a contractor that is not Shilo. The portion of previously buried piping that is uncovered measured only 3'-6" below grade. The portion that Shilo has installed is buried at the correct depth. The previously installed piping needs to be dug up and re-installed at a minimum 4'-6" bury depth as per Ordinance and plans. No piping is to be covered at this time.
FIR13-00223 FIR-Aging Inspection2/24/20162/24/20162/24/2016 2:19:21 PMPCANC
Rescheduled for tomorrow morning
FIR15-00618 INSP-Final Inspection2/23/20162/24/20162/24/2016 1:49:02 PMPFAIL
Will be ok to final when the SImplex permit for the dialer is finaled.
FIR15-00513 INSP-Final Inspection2/23/20162/24/20162/24/2016 1:41:55 PMPPASS
Permit finaled
FIR16-00032 INSP-Sprinkler Rough-in/Hydro2/24/20162/24/20162/24/2016 12:15:17 PMPPASS
All sprinkler work is complete except for the two tamper switches being connected to the facp
BLD15-02562 FIRE-Final Inspection2/24/20162/24/20162/24/2016 11:53:41 AMPPASS
life safety passed
BLD15-02559 FIRE-Final Inspection2/24/20162/24/20162/24/2016 11:22:36 AMPPASS
Life safety passed
FIR15-00711 INSP-Final Inspection2/24/20162/24/20162/24/2016 11:09:46 AMPPASS
Permit finaled
BLD15-02561 FIRE-Final Inspection2/24/20162/24/20162/24/2016 11:08:07 AMPPASS
Life safety passed
FIR09-00051 FIR-Aging Inspection2/24/20162/24/20162/24/2016 10:43:24 AM NR
Contractor is out of business and sold accounts to Taylor Brothers.
BLD15-02842 FIRE-Conference2/24/20162/24/20162/24/2016 8:56:28 AMADONE
Dutch and I went over life safety requirements for the north half of the building
NAF15-00045 INSP-Final2/23/20162/24/20162/24/2016 8:53:03 AMAFAIL
Project is not ready for final as requested. Project is not ready for rough-in yet. Missing earthquake bracing, missing upright coverage in pockets at the main entry, pipe sizing of riser nipples and starter pieces do not match the approved plans, missing dry sidewall heads in the exterior pockets. I gave the general contractor the ok to cover hard lids as indicated on the plans. Resubmittals are required showing all changes such as piping size changes and the additional fittings used, and additional sprinkler heads.