BLD18-03660
| FIRE-Final Inspection | 2/26/2019 | 2/26/2019 | 2/26/2019 2:50:26 PM | P | PASS |
|
|
life safety passed
Call half hour before // Sean Phone #: ###-####
|
FIR19-00115
| INSP-Final Inspection | 2/26/2019 | 2/26/2019 | 2/26/2019 1:42:09 PM | P | PASS |
|
|
Permit finaled
|
FIR18-00901
| INSP-Supply line flush | 2/25/2019 | 2/26/2019 | 2/26/2019 1:41:46 PM | A | PART |
|
|
The portion of the supply piping near the Suez connection point is not buried deep enough and will need to be modified and re-inspected. After the second 45 degree elbow the piping is deep enough and can be buried.
Note:Pouring Thrust Block by noon. P Lease see Troy Nelsen Phone #: ###-#### Inspection requested via web by Daniel Buccino
|
BLD19-00180
| FIRE-Final Inspection | 2/26/2019 | 2/26/2019 | 2/26/2019 1:06:31 PM | P | FAIL |
|
|
Finish installing the ceiling tile and repair the exit signs at the front and rear doors.
John Phone #: ###-####
|
BLD19-00180
| FIRE-Sprinkler Rough-in | 2/26/2019 | 2/26/2019 | 2/26/2019 12:07:04 PM | P | CANC |
|
|
Wrong inspection type scheduled. John Phone #: ###-####
|
FIR19-00115
| INSP-Sprinkler Rough-in | 2/26/2019 | 2/26/2019 | 2/26/2019 12:05:43 PM | P | PASS |
|
|
Rough-in passed. Piping can be covered.
|
BLD17-02434
| FIRE-Final Inspection | 2/25/2019 | 2/26/2019 | 2/26/2019 11:00:30 AM | A | FAIL |
|
|
Per conversation with Chad BME will be pulling a separate permit for suite #108.
Suite #108 items needing correction are: sprinkler modifications, sprinkler monitoring, repair exit sign, remove thumbturn deadbolt at exits.
Suite #102 (this tenant in all other spaces) needs : thumbturn deadbolt removed from exterior and interior exits, ceiling tile installed in mechanical room, bent sprinkler head repaired at overhead door, racking permit for racks over 8', exterior door hardware, possible deleting Paint Room door (need plan review approval), provide sprinkler coverage under paint room door, repair insulation at roof deck in Paint Room, Paint Room process needs plan review approval, door sticker at main exit needs provided, sprinkler piping hanger on second floor needs repaired. See city approved plans for items high lighted.
Chad Phone #: ###-####
|
BLD17-02437
| FIRE-Final Inspection | 2/25/2019 | 2/26/2019 | 2/26/2019 10:54:03 AM | A | FAIL |
|
|
Provide racking permit, provide verification of possible high pile storage permit for the encapulated bags of insulation, provide sticker at main exit door.
Chad Phone #: ###-####
|
BLD17-02439
| FIRE-Final Inspection | 2/25/2019 | 2/26/2019 | 2/26/2019 10:52:40 AM | A | FAIL |
|
|
Provide correct exit door hardware. See city approved plans for items high lighted.
Chad Phone #: ###-####
|
BLD17-02436
| FIRE-Final Inspection | 2/25/2019 | 2/26/2019 | 2/26/2019 10:51:59 AM | A | FAIL |
|
|
Tag and mount the fire extinguisher, provide correct exit door hardware. See city approved plans for items high lighted.
Chad Phone #: ###-####
|
BLD18-00943
| FIRE-Conference | 2/25/2019 | 2/26/2019 | 2/26/2019 8:55:52 AM | A | DONE |
|
|
Russel and I spoke about temp. occupancy requirements and exit paths. I deferred him to Ron Hill in project management. Phone #: ###-#### Inspection requested via web by Russell Valline
|
BLD16-03429
| FIRE-Final Inspection | 2/25/2019 | 2/26/2019 | 2/26/2019 8:54:43 AM | A | PASS |
|
|
life safety passed. please call for access, Dave Phone #: ###-####
|
BLD19-00161
| FIRE-Final Inspection | 2/25/2019 | 2/26/2019 | 2/26/2019 8:02:47 AM | A | PASS |
|
|
Life safety passed
sid Phone #: ###-####
|