BLD18-04246
| FIRE-Final Inspection | 2/4/2019 | 2/4/2019 | 2/4/2019 3:12:01 PM | P | FAIL |
|
|
Need the project related fire alarm permit finaled, need door hardware installed, need fire extinguishers. Exit lights/emergency lights did function.
Tony Phone #: ###-####
|
FIR18-00965
| INSP-Final Inspection | 2/4/2019 | 2/4/2019 | 2/4/2019 3:07:58 PM | P | PASS |
|
|
permit finaled
Tony Phone #: ###-####
|
FIR17-00626
| INSP-Final Inspection | 2/4/2019 | 2/4/2019 | 2/4/2019 1:42:19 PM | P | PART |
|
|
Todays inspection was to verify that the fiber optic interconnection is functional which it was.
ARFF added to all devices descriptions going to the main panel. Phone #: ###-#### Inspection requested via web by Gary Gambino
|
NAF18-00086
| INSP-Sprinkler Rough-in | 2/4/2019 | 2/4/2019 | 2/4/2019 1:40:06 PM | P | PASS |
|
|
The pendant head on the third floor has been moved and is passed. Piping can not be covered until a tenting inspection has been passed.
Contact Andrew Larson ###-#### 0 Min Prior to RTC Insp start please for Lot A5.
Thank YOU Phone #: ###-#### Inspection requested via web by Teri Cruickshank
|
FIR18-00600
| INSP-Final Inspection | 2/1/2019 | 2/4/2019 | 2/4/2019 1:37:49 PM | P | CANC |
|
|
Phone #: ###-#### >> Inspection requested via web by Don Kartchner Inspection cancelled from web by: Don Kartchner
|
NAF18-00128
| INSP-Sprinkler Rough-in | 2/4/2019 | 2/4/2019 | 2/4/2019 12:30:52 PM | P | PASS |
|
|
The remaining sprinkler piping is ok for cover.
Call prior to going Phone #: 2086956553 >> Inspection requested via mobile web by John Venche
|
NAF18-00086
| INSP-Sprinkler Rough-in | 2/1/2019 | 2/4/2019 | 2/4/2019 10:44:13 AM | A | PART |
|
|
See the city approved plans for the appartment that was inspected. The first and second floor piping can be covered but the third floor needs one pendant head adjusted to provide coverage and tenting approved prior to a cover approval. Andrew will reschedule a nother inspection for this afternoon to see tyhe head modified.
Contact Andrew Larson ###-#### 0 Min Prior to RTC Insp start please for Lot A5.
Thank YOU Phone #: ###-#### Inspection requested via web by Teri Cruickshank
|
FIR19-00012
| INSP-Final Inspection | 2/1/2019 | 2/4/2019 | 2/4/2019 9:18:31 AM | A | FAIL |
|
|
Rough-in passed for the most part. There were no small documents, will need 200lb hydro, 24 hr air, trip test....ect. prior to a final.
please give half hour notice Phone #: ###-#### Inspection requested via web by jeremiah robison
|