Inspections for the day of: Tuesday, February 6, 2018.
Number of inspections: 12
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorTroy Cobbley
TitleFIRE INSPECTOR
Phone #794-9483
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
BLD17-02915 FIRE-Final Inspection2/6/20182/6/20182/6/2018 3:16:48 PMPCANC
Hugo Phone #: ###-####
FIR17-00756 INSP-Final Inspection2/6/20182/6/20182/6/2018 1:57:21 PMPFAIL
Need correct suite number, all of the wall mounted strobes are too low, the 15cd ceiling mounted strobes can't be over 10' and the 95cd strobe in the Lobby is overspaced. No actual testing of devices happened. As-builts will need to be submitted to the plan reviewer prior to a final sign off.


Contact is Sean Phone #: ###-#### Inspection requested via web by Morgan Ahten
BLD17-03877 FIRE-Final Inspection2/5/20182/6/20182/6/2018 1:55:38 PMAFAIL
Life safety will be ok to pass when the project related fire alarm permit is finaled.


Jim Phone #: ###-#### Inspection requested via web by Jim Wellman
FIR17-00462 INSP-Sprinkler Rough-in2/6/20182/6/20182/6/2018 1:21:15 PMPPASS
The underground supply line is ok for cover.
FIR17-00455 INSP-Sprinkler Rough-in2/6/20182/6/20182/6/2018 1:21:00 PMPPASS
The underground supply line is ok for cover.
FIR17-00441 INSP-Sprinkler Rough-in2/6/20182/6/20182/6/2018 1:20:46 PMPPASS
The underground supply line is ok for cover.
FIR17-00451 INSP-Sprinkler Rough-in2/6/20182/6/20182/6/2018 1:20:27 PMPPASS
The underground supply line is ok for cover.
BLD17-03529 FIRE-Final Inspection2/6/20182/6/20182/6/2018 12:49:56 PMPFAIL
Provide city approved plans/small documents, hang fire extinguisher, repair emergency light in back room, provide fire sprinkler permit for the relocation of the sprinkler pendants that are located too close to one another.

Devin Phone #: ###-####
FIR17-00741 INSP-Final Inspection2/5/20182/6/20182/6/2018 11:32:33 AMAPASS
Permit finaled
FIR17-00541 INSP-Sprinkler Rough-in/Hydro2/5/20182/6/20182/6/2018 10:32:56 AMAPASS
The second floor and pre-action system 200lb hydro tests passed.
FIR18-00078 INSP-Final Inspection2/5/20182/6/20182/6/2018 8:29:42 AMAPASS
permit finaled

Adam Phone #: ###-####
FIR18-00078 INSP-Sprinkler Rough-in2/5/20182/6/20182/6/2018 8:29:16 AMAPASS
Adam Phone #: ###-####