BLD18-02644
| FIRE-Conference | 3/18/2019 | 3/18/2019 | 3/18/2019 3:17:42 PM | P | DONE |
|
|
Jason and I spoke about fire sprinkler and fire alarm isuues that need addressed prior to a phase 1 approval.
|
FIR19-00120
| INSP-Sprinkler Rough-in | 3/15/2019 | 3/18/2019 | 3/18/2019 3:14:31 PM | P | PASS |
|
|
Rough-in passed. Piping can be covered. Gabe and I spoke about cpvc riser requirements.
Gabe Garduno is the contact. Thank you for your hard work! Phone #: ###-#### Inspection requested via web by Stan Beus
|
BLD18-00943
| FIRE-Conference | 3/17/2019 | 3/18/2019 | 3/18/2019 12:09:34 PM | A | DONE |
|
|
I went over general life safety items with Russell. There were no small documents on site. Phone #: ###-#### Inspection requested via web by Russell Valline
|
BLD18-03106
| FIRE-Final Inspection | 3/18/2019 | 3/18/2019 | 3/18/2019 10:48:48 AM | P | PASS |
|
|
Life safety passed
|
FIR18-00244
| INSP-Final Inspection | 3/18/2019 | 3/18/2019 | 3/18/2019 10:28:18 AM | P | PASS |
|
|
Permit finaled
|
FIR18-00244
| INSP-Sprinkler Rough-in/Hydro | 3/18/2019 | 3/18/2019 | 3/18/2019 10:27:57 AM | P | CANC |
|
|
Wrong inspection type scheduled.
|
FIR18-00675
| INSP-Sprinkler Rough-in/Hydro | 3/15/2019 | 3/18/2019 | 3/18/2019 10:26:36 AM | P | CANC |
|
|
Not ready for inspection yet after onsite visit with Robert during a conference with the General Contractor. Will need city approved drawings and we also discussed the need for a hydro test for the phase 1 area. Will be rescheduled for the morning. Robert Phone #: ###-####
|
FIR18-00560
| INSP-Final Inspection | 3/14/2019 | 3/18/2019 | 3/18/2019 9:06:53 AM | A | PASS |
|
|
Permit finaled
RICK FRY IS OUR CONTACT. Phone #: ###-#### Inspection requested via web by Brad Bettencourt
|