Inspections for the day of: Wednesday, March 20, 2019.
Number of inspections: 11
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorTroy Cobbley
TitleFIRE INSPECTOR
Phone #794-9483
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
FIR18-00545 INSP-Supply line flush3/18/20193/20/20193/20/2019 2:58:45 PMPPASS
Underground flush witnessed by Mark Scharfen on 3/22/2019-building D was witnessed by Troy Cobbley and Mark Scharfen but wrong permit was signed off.


Gerardo Arce is the contact. Thank you for your hard work! Phone #: ###-#### Inspection requested via web by Stan Beus
FIR18-00562 INSP-Supply line flush3/18/20193/20/20193/20/2019 2:57:53 PMPPASS
underground flush witnessed.

Gerardo Arce is the contact. Thank you for your hard work! Phone #: ###-#### Inspection requested via web by Stan Beus
BLD18-04066 FIRE-Final Inspection3/20/20193/20/20193/20/2019 2:56:04 PMPPART
A temporary for life safety is being given until the deadbolt has been removed from the west exit door and approved hardware provided.
BLD18-04501 FIRE-Final Inspection3/19/20193/20/20193/20/2019 2:18:26 PMPPASS
Life safety passed pending the installation of the CO detector. Inspection by Mark Scharfen.

Keith Phone #: ###-####
FIR18-00804 INSP-Sprinkler Rough-in/Hydro3/20/20193/20/20193/20/2019 1:32:31 PMPCANC
To be rescheduled for tomorrow. This Rough-in/Hydro is for wings A ; B. The contact is Richard Clark. Thank you for your hard work! Phone #: ###-#### Inspection requested via web by Stan Beus
FIR18-00510 INSP-Sprinkler Rough-in3/19/20193/20/20193/20/2019 1:32:03 PMPPASS
Piping above soffits in units 209, 211, 212, 213, 214, 215 and Corridor 2 is ok for cover.

Rough in for second floor Phone #: ###-#### Inspection requested via web by Sam Ball
FIR18-00675 INSP-Final Inspection3/19/20193/20/20193/20/2019 1:30:55 PMACANC
To be rescheduled for tomorrow. Robert Phone #: ###-####
FIR18-00675 INSP-Sprinkler Rough-in/Hydro3/19/20193/20/20193/20/2019 1:30:32 PMAPASS
Overhead hydro test passed for the phase 1 area. Need to add sprinkler coverage in Display/Trophy case as discussed. Need plan modes for additional 90's for the remote area under the mezzanine.

Robert Phone #: ###-####
FIR19-00185 INSP-Final Inspection3/19/20193/20/20193/20/2019 9:53:50 AMPPASS
Permit finaled


Please call Payden for access Phone #: ###-####
FIR19-00185 INSP-Sprinkler Rough-in3/19/20193/20/20193/20/2019 9:53:10 AMAPASS
Rough-in passed. Piping can be covered. Please call Payden for access-Phone #: ###-####
BLD19-00790 FIRE-Final Inspection3/19/20193/20/20193/20/2019 9:35:05 AMAPASS
Conducted life safety inspection. Exit lights/Emergency lighting fire extinguishers and occupant load sign passed. Per discussion with owner CO system for taps will only have 1 50 lb tank that will be removed prior to building final.

mark scharfen Joe Phone #: ###-####