FIR19-00831
| INSP-Sprinkler Rough-in | 3/23/2020 | 3/23/2020 | 3/23/2020 2:14:35 PM | P | FAIL |
|
|
I stopped at the project three times but the backing for the insulation is not done yet.
|
FIR19-00933
| INSP-Sprinkler Rough-in | 3/23/2020 | 3/23/2020 | 3/23/2020 2:13:29 PM | P | PASS |
|
|
Hangers changed to approved attachment, flexible cplgs added at rise up and two additional heads added on the back side of duct work. One additional hard lid is ok for cover.
We fixed deficiencies would like to have it rechecked. Phone #: ###-#### Inspection requested via web by Sam Ball
|
FIR18-00892
| INSP-Final Inspection | 3/19/2020 | 3/23/2020 | 3/23/2020 10:45:45 AM | P | PASS |
|
|
Permit finaled. Phone #: ###-#### Inspection requested via web by Connie Danes
|
NAF18-00114
| INSP-Final | 3/20/2020 | 3/23/2020 | 3/23/2020 9:31:04 AM | A | FAIL |
|
|
Provide Opti-con entry system for the electric gate per the Garden City Ordinance.
Call prior to going Phone #: 2088503882 >> Inspection requested via mobile web by Chris
|