FIR18-00654
| INSP-Sprinkler Rough-in/Hydro | 4/12/2019 | 4/12/2019 | 4/12/2019 2:50:44 PM | P | PASS |
|
|
The underground hydro test was witnessed with no visible loss on the guage. Per conversation with the general contractor it appears that there will be adequate coverage for the underground supply piping when the asphalt has been installed. See previous entry for coverage concerns.
|
FIR18-00670
| INSP-Final Inspection | 4/10/2019 | 4/12/2019 | 4/12/2019 2:45:33 PM | P | FAIL |
|
|
Overhead hydro test failed due to visible loss on the guage.Separate inspection needs to be scheduled for a hydro test or rough-in.
Please call Chris ford Phone #: ###-#### Inspection requested via web by Jessia Maxwell
|
FIR19-00159
| INSP-Final Inspection | 4/11/2019 | 4/12/2019 | 4/12/2019 2:18:14 PM | P | FAIL |
|
|
Not ready for final due to delays caused by the door installer. I did perform a rough-in inspection for the south warehouse sprinkler system which passed.
Please cordinate final with Troy Nelson Phone #: ###-#### Inspection requested via web by Christophe Wilson
|
FIR18-00853
| INSP-Final Inspection | 4/12/2019 | 4/12/2019 | 4/12/2019 2:16:54 PM | P | CANC |
|
|
Not ready for final yet due to the fire sprinkler contractor starting 2 hour hydro testing for the overhead and underground.
Call prior to going Phone #: 2088301311 >> Inspection requested via mobile web by Nathan Price
|
BLD19-00343
| FIRE-Final Inspection | 4/10/2019 | 4/12/2019 | 4/12/2019 1:39:32 PM | A | PASS |
|
|
Life safety passed. Solid shelving is of per Mark as long a total shelf area does not exceed 20 sq. ft.
Derreck Carlson Phone #: ###-#### Inspection requested via web by Jeff Higgins
|
FIR19-00215
| INSP-Sprinkler Rough-in | 4/11/2019 | 4/12/2019 | 4/12/2019 12:25:41 PM | A | PART |
|
|
See the city approved plans for several locations on the second floor where piping is marked "ok" for cover. Plan mods are needed for pipe routing changes. Possible additional heads will be required due to soffits being added.
Gabe Garduno is the contact. He wants this to be a partial rough-in. Thank you for your hard work! Phone #: ###-#### Inspection requested via web by Stan Beus
|
FIR18-00525
| INSP-Sprinkler Rough-in | 4/11/2019 | 4/12/2019 | 4/12/2019 11:26:37 AM | A | PART |
|
|
First floor rough-in complete. Second floor rough-in is partial due to time constraints. See the city approved plans for corrections needed. Plan mods may be required due to the additional fittings in many of the branchlines/mains.
Todd Ketterling is the contact. Thank you for your hard work! Phone #: ###-#### Inspection requested via web by Stan Beus
|
FIR18-00835
| INSP-Final Inspection | 4/11/2019 | 4/12/2019 | 4/12/2019 11:22:33 AM | A | FAIL |
|
|
Permit will be ok to final when documents are provided to plan review that address the supervisory/rrouble on panel as per revios corretion
John Howard, Technician Phone #: ###-#### Inspection requested via web by John Siewert
|
NAF19-00019
| INSP-Sprinkler Rough-in/Hydro | 4/11/2019 | 4/12/2019 | 4/12/2019 10:15:13 AM | A | PASS |
|
|
The underground hydro test was witnessed with no pressure loss. Call prior to going Phone #: 2089148171 >> Inspection requested via mobile web by Brian
|
NAF17-00077
| INSP-Final | 4/11/2019 | 4/12/2019 | 4/12/2019 10:14:37 AM | A | FAIL |
|
|
Provide fire dept access signage as discussed and shown on the review comments.
Call prior to going Phone #: 2086972714 >> Inspection requested via mobile web by BRAD Cooper
|