BLD18-04004
| FIRE-Conference | 5/1/2019 | 5/1/2019 | 5/1/2019 2:38:31 PM | P | DONE |
|
|
Per the general contractor a barrier is going to be installed above the cooler to provide separation.
|
FIR19-00287
| INSP-Sprinkler Rough-in | 5/1/2019 | 5/1/2019 | 5/1/2019 2:37:48 PM | P | PASS |
|
|
Rough-in passed. Piping can be covered.
Adam Phone #: ###-####
|
BLD18-04335
| FIRE-Final Inspection | 5/1/2019 | 5/1/2019 | 5/1/2019 1:26:40 PM | P | PASS |
|
|
Life safety passed. The fire sprinkler issue has been corrected so no need for a temporary occupancy for life safety. AJ Phone #: ###-####
|
FIR19-00299
| INSP-Final Inspection | 5/1/2019 | 5/1/2019 | 5/1/2019 1:25:54 PM | P | PASS |
|
|
Permit finaled
Contact Nick---ASAP if possible. Thank you Phone #: ###-#### Inspection requested via web by Chris Green
|
FIR19-00096
| INSP-Final Inspection | 4/30/2019 | 5/1/2019 | 5/1/2019 12:20:34 PM | A | PASS |
|
|
Permit finaled
All finish pieces are on thank you Phone #: ###-#### Inspection requested via web by jeremiah robison
|
FIR18-00610
| INSP-Sprinkler Rough-in/Hydro | 4/30/2019 | 5/1/2019 | 5/1/2019 12:15:55 PM | A | PASS |
|
|
The overhead hydro tests on all systems have been witnessed with no loss at the guage. Mike Phone #: ###-####
|
FIR19-00291
| INSP-Final Inspection | 4/30/2019 | 5/1/2019 | 5/1/2019 9:45:24 AM | A | PASS |
|
|
Permit finaled. contact Roy Phone #: ###-#### Inspection requested via web by Chris Green
|
FIR19-00291
| INSP-Sprinkler Rough-in | 4/30/2019 | 5/1/2019 | 5/1/2019 9:44:37 AM | A | PASS |
|
|
Rough-in passed. contact Roy Phone #: ###-#### Inspection requested via web by Chris Green
|
FIR17-00612
| INSP-Sprinkler Rough-in | 4/30/2019 | 5/1/2019 | 5/1/2019 9:44:01 AM | A | DONE |
|
|
24 hour air test started at 9:30 with 49psi on the guage.
Jon Beazer is the contact. This is for a 24 hour air test (part 1), to be preformed in the vacant space next to Rite Aid in the back. Thank you for your hard work! Phone #: ###-#### Inspection requested via web by Stan Beus
|
FIR19-00249
| INSP-Sprinkler Rough-in | 4/30/2019 | 5/1/2019 | 5/1/2019 8:06:30 AM | A | PASS |
|
|
Rough-in passed. Piping can be covered.
Adam Phone #: ###-####
|
BLD18-00999
| FIRE-Final Inspection | 4/30/2019 | 5/1/2019 | 5/1/2019 7:31:20 AM | A | PASS |
|
|
life safety passed
Phone #: ###-#### Inspection requested via web by Joel Hartman
|