FIR16-00293
| INSP-Alarm Testing | 5/17/2016 | 5/17/2016 | 5/17/2016 2:13:41 PM | P | DONE |
|
|
See the city approved plans for area/devices tested.
|
FIR13-00485
| FIR-Aging Inspection | 5/17/2016 | 5/17/2016 | 5/17/2016 1:43:56 PM | | NR |
|
|
Jeff is going to follow up on project status
|
BLD16-00451
| FIRE-Final Inspection | 5/16/2016 | 5/17/2016 | 5/17/2016 12:43:19 PM | P | PASS |
|
|
life safety passed. I dicussed with James that a racking permit may be required due to the storage racks that exceed 8'. They are light duty racks.
|
FIR16-00225
| INSP-Final Inspection | 5/16/2016 | 5/17/2016 | 5/17/2016 12:42:09 PM | A | PASS |
|
|
Permit finaled
|
FIR16-00253
| INSP-Final Inspection | 5/16/2016 | 5/17/2016 | 5/17/2016 12:41:26 PM | A | FAIL |
|
|
Can't cover yet since insulation is still hanging down blocking the upright sprinkler heads in two locations. Also Don and I discussed the overspaced pendants in the Dining area. It looks like he will need to add two pendants to provide the required coverage.
|
BLD16-00170
| FIRE-Final Inspection | 5/17/2016 | 5/17/2016 | 5/17/2016 10:31:40 AM | P | PART |
|
|
A temporary for life safety is being given with Scott's approval for a maximum of 30 days and only for the moving in of equipment. A final can be given when the project related fire alarm permit is finaled.
|
BLD15-04346
| FIRE-Conference | 5/17/2016 | 5/17/2016 | 5/17/2016 9:03:04 AM | P | DONE |
|
|
After dicussing lack of slope in the FIre Pump Room with Scott Arellano I spoke to the project superintendant about the floor slope issue and that there would be no final sign off on the life safety until the floor had been sloped as per previous discussions.
|
FIR16-00131
| INSP-Conference | 5/17/2016 | 5/17/2016 | 5/17/2016 9:01:30 AM | P | DONE |
|
|
After dicussing lack of slope in the FIre Pump Room with Scott Arellano I spoke to the project superintendant about the floor slope issue and that there would be no final sign off on the life safety until the floor had been sloped as per previous discussions.
|
FIR16-00131
| INSP-Sprinkler Rough-in | 5/16/2016 | 5/17/2016 | 5/17/2016 8:20:20 AM | A | PASS |
|
|
Four pendant heads as marked on the drawings are ok for cover. I noted that the Fire Pump Room floor has not been sloped except for maybe a 1'-0" circle around the floor drain which is positioned next to the north wall. I spoke to the job superintendant again and deferred him to Scott Arellano.
|
BLD15-04503
| FIRE-Final Inspection | 5/16/2016 | 5/17/2016 | 5/17/2016 7:56:15 AM | A | PASS |
|
|
life safety passed
|
FIR16-00245
| INSP-Final Inspection | 5/16/2016 | 5/17/2016 | 5/17/2016 7:45:31 AM | A | PASS |
|
|
Permit finaled
|